background image

 

ATTENTION!

T

HE

 

LIVE

 

ELECTRIC

 

DEVICE

!

Before doing any activities connected with power supply (connecting wires, 

installation of the device, etc) it is necessary to make sure that the regulator is not 
connected to the grid!

Assembly and installation should only be carried out by qualified electrician.
Before activating the controller it is necessary to do the measurement of 

effectiveness   of   resetting   electric   motors,   a   boiler   and   the   measurement   of 
insulation of electric wires.

You   mustn’t   use   any   shut-off   valves   that   shut   off   central   heating   water 

circulation.

The regulator mustn’t work in closed system of central heating. There must 

be   mounted   pop   valves,   pressure   valves   and   expansion   tank   that   protect   the 
boiler from boiling water in the central heating system.

The controller MUST be connected to the socket with earthing. While 

connecting the controller you must do the measurement of effectiveness of 

earthing. Cables cannot be exposed to temperature above 90°C. You must 

isolate them from elements of the stove that can warm up to high 

temperatures.