9
Interchanging connections
For optimum matching of the pipelines to the freshwater station it is possible to interchange the con
-
nections (right/left). This does not change venting of the primary circuit, however.
Procedure:
1. Demounting of pipe elements 1 - 4 including pump from the heat exchanger
2. Removal of the pump and installation in the correct position.
3. Remount pump connection plug 5 on the other side.
4. Mounting of pipe elements 1 - 4 and the pump on the heat exchanger (see figures above) on the
other side, correct positional setup of the volume flow sensor
5. Commissioning according to the "Commissioning" chapter
Important:
The primary and secondary connections must be exchanged together!
1
1
2
2
3
4
5
3
4
Pump connection-plug
Version
„Pump right“
Version
„Pump left“