Once that all the panels are fi xed, it is neces-
sary to connect the heater. It must pass throu-
gh the hole placed on the cap of the front pa-
nel (see picture nr 4).
7.
After that it is necessary to lift the cover
where the terminal is, making action on
the screws, and conncet the 2 ends of the
heater, one in correspondence with brown
cables, and one in correspondence with blu
cables. (See picture nr 5).
8.
It is now possible to connect the energy
supply cables and switch on the miniroom,
by pressing the green botton.
INSTALLATION OF THE SHELVES
9.
Apply on the side wall holes the plastic sup-
ports (12 pieces) that are supplied by the
producer. The support must be applied in
the same position both on the right side and
on the left side of the wall (see picture 6).
10.
Lay down every single shelf on 4 plastic sup-
ports.
INSTALLATION OF THE MEAT HOOK
11.
Insert into the hole on the side wall the
end of the hook and fi x it to the deep bottom
(see picture 7). After that let it slip into the
opposite side wall hole.