________________________________________________________________________________
EVO STAR 60-800
24
5 STARTING-UP AND SHUTTING DOWN THE
MACHINE
5.1 STARTING-UP THE MACHINE
CAUTION! : IF THE BATTERY BREAKER IS CLOSED, BEFORE STARTING UP T2000,
THIS CAN CAUSE U.P.S DAMAGE.
5.1.1U.P.S with independent reserve line
1.
Make sure that the wires are correctly connected respecting the cyclic sense of the phases U,V,W
2.
Make sure that the “Manual By-pass” switch is turned off and blocked by its blocking device
3.
Give power to the mains
4.
Close the “Reserve switch” breaker, the display will turn on and the message “UPS STOPPED” will appear, all the
synoptic led’s will be red except led “H ” which remain green; wait till led “A” start flashing, if this does not
happen the supply voltage is not adequate or the cyclic sense of the phases is incorrect, therefore you must
disconnect the equipment, verify the connections and start this procedure again from the beginning.
5.
Close the “Mains switch” and “Output switch” breakers, led’s “G and B” will turn green
6.
Press the
button for about two seconds, on the display the message “switch on procedure started” will appear,
if the steps of procedure have been followed correctly led “C” and led “E” will become green and the message
“UPS in alarm mode” will appear
7.
Once you have carried out the turning on procedure and led’s “C” and “E” are green, it is possible to close the
“Battery switch” breaker and led “D” will be green.
8.
If installation has been correctly carried out and the turning on procedure done successfully, the message “UPS in
normal operation operation” will appear and all the synoptic led’s will be green
9.
Go to paragraph 5.1.2
5.1.2 First time starting-up
If the turning on procedure has been carried out for the first time we advise you to continue this procedure to verify the
real efficiency and to get familiar with the system
1.
Select the language you wish to use by following the indications in the menu (diagram 1a/b)
2.
Carry out the battery test (see 6.1.2.2) and verify the outcome
3.
Carry out the complete by-pass procedure with the U.P.S. switched on (paragraph 5.1) and all operations to restore
the by-pass
4.
Carry out a power shortage test by turning off the “Mains switch” and make sure that the U.P.S. goes into alarm
mode and that led D starts flashing and led F stays green (picture 1and 7) then turn on the “Mains switch” and
check that normal functioning has been restored.