3
Safety of installation
01. Leave space for maintenance. Install the machine so that the covers of the machine can be opened
without interference.
02. Make sure that the ground strong enough to support the machine.
03. Only an authorized electrical technician should perform work with the power cable connections.
04. Make sure that all bolts are tightened securely.
05. Make sure that all related hoses is connected secure.
06. The machine should be operated by one, well-trained person only. Injury can occur if more than
one person operates the machine. If more than one operator is absolutely necessary, all involved
operators must cooperate and be able to communicate.
07. Never start machine operation without the safety devices in place.
08. Construction work of tower or supporting frame must be done by professional installation
personnel, electrical wire must be qualified product and wiring work be done by professional and
qualified personnel. Construction work, wiring products and electrical installation personnel must
be in accordance with construction regulation standard.
09. Related permission certificates and engineering certificates are required for safe installation.
Location of tower, tower and tower foundation must be professionally designed. Soil and wind
field status must be put into consideration when selecting a location. Tower must keep far away
from buildings, neighboring properties or electrical power lines. Do not attempt to climb the tower,
only experienced personnel with adequate safety equipment is allowed to climb the tower. It is
recommended that when installing tower, keep it away from buildings and electrical power lines
for at least 100 meters (300 feet).
10. The construction and wiring process must be in accordance with electrical engineering
regulations.
11. Never remove the covers unless absolutely necessary.
12. These equipments must have proper heat elimination function; air current jam may bring fire
disaster.
Safety of machinery
01. Never remove the covers unless absolutely necessary.
02. Never put any tools or instruments on the machine operation panel or on any machine part.
03. Be careful not to operate the wrong switch. Visually check the switches on the operation panel
before operating them.
04. Never change the parameter setting without consulting your local representative. If changed
inadvertently, some parameters will cancel interlock setting.
05. Wiring work for 200 VAC or higher voltage circuits must be performed only by an authorized
electrical technician.