INSTALLATION
3.Installation
3.1 Introduction
In this chapter contains a detailed description about the unpacking, installation and
inspection procedures. When the furnace is moved in transit and during final placement at
the customer's facility, care should be exercised at all times.
CAUTION
Transport of the system should be in an upright position
at all times.
3.2 Unpacking
•
Before the furnace is unpacked, a visual inspection of packing materials should be
made. If there is evidence of damage during transport, the carrier should be
contacted so that an inspector can be present to verify any damage before the
furnace is unpacked.
•
If there is any visible damage, notify Amtech/Tempress Systems verbally and in
writing. This must be done within 24 hours, after arrival of the shipment.
•
A forklift truck, with a minimum capacity of 1500 kg, is recommended to be
available to move/carry the furnace in its right place.
CAUTION
The furnace is packed in 2 layers of plastic. The first layer
must be removed outside the clean room. The second
layer must be removed in the clean room.
Unpacking:
•
Check off all boxes against the packing list.
•
Unpack the boxes one by one.
•
Check the contents of the boxes against the collo contents list
•
If any damage is visible, then....
CAUTION
Do not dispose any of the packing materials or boxes.
•
Release and remove equipment wrappings.
F
URNACE
R
EFERENCE
M
ANUAL
3-1