Primary Boom Components
Part No. 1268515GT
Z
®
-34/22 Bi-Energy
29
5 Attach a lifting strap from an suitable lifting
device to the primary boom lift cylinder.
6 Remove the rear turntable cover.
7 Place a 4x4 inch / 10 x 10 cm block between
the lower compression arms and the cross
member of the upper secondary boom.
Carefully lower the secondary boom onto the
block.
Crushing hazard. Keep hands
away from the block and all
moving parts when lowering the
secondary boom.
8 Remove the pin retaining fasteners from the
primary boom lift cylinder rod-end pivot pin.
Use a soft metal drift to remove the pin.
Bodily injury hazard. Spraying
hydraulic oil can penetrate and
burn skin. Loosen hydraulic
connections very slowly to allow
the oil pressure to dissipate
gradually. Do not allow oil to
squirt or spray.
9 Lower the rod end of the cylinder onto the
blocks that were placed on the upper
secondary boom.
10 Remove the pin retaining fasteners from the
upper compression arm pivot pin (same side
of machine as the primary boom lift cylinder
barrel-end pivot pin retaining fasteners).
11 Place a rod through the compression arm
pivot pin and twist to remove the pin.
12 Swing the compression arm up out of the way
and secure it from moving.
13 Tag, disconnect and plug the primary boom
lift cylinder hydraulic hoses. Cap the fittings
on the cylinder.
Bodily injury hazard. Spraying
hydraulic oil can penetrate and
burn skin. Loosen hydraulic
connections very slowly to allow
the oil pressure to dissipate
gradually. Do not allow oil to
squirt or spray.
14 Support the primary boom lift cylinder with
straps or ropes to restrict it from swinging
freely when the barrel-end pivot pin is
removed.
15 Remove the pin retaining fasteners from the
lift cylinder barrel-end pivot pin. Do not
remove the pivot pin.
16 Use the suitable lifting device to raise the
primary boom 1 inch / 2.5 cm. This will relieve
pressure on the barrel-end pivot pin.
17 Place a rod through the barrel-end pivot pin
and twist to remove the pin.
Crushing hazard. The primary
boom could become unbalanced
and fall when removed from the
machine if not properly attached
to the suitable lifting device.
18 Attach a lifting strap from an suitable lifting
device to the rod end of the primary boom lift
cylinder. Carefully loosen the straps and allow
the barrel end of the primary boom lift cylinder
to slowly swing down.
19 Carefully remove the cylinder from the
machine.
Summary of Contents for Genie Z-34/22
Page 63: ...October 2021 Service and Repair Manual Manifolds Part No 1268515GT Z 34 22 Bi Energy 51 ...
Page 89: ...October 2021 Service and Repair Manual 77 Electrical Schematic ANSI CSA from SN Z34F 12066 ...
Page 92: ...Service and Repair Manual October 2021 80 Electrical Schematic ANSI CSA from SN Z34F 12066 ...
Page 97: ...October 2021 Service and Repair Manual 85 PBOX Wiring Diagram ANSI CSA from SN Z3414 9686 ...
Page 103: ...October 2021 Service and Repair Manual 91 Electrical Schematic CE AS from SN Z34F 12066 ...
Page 106: ...Service and Repair Manual October 2021 94 Electrical Schematic CE AS from SN Z34F 12066 ...
Page 114: ...Service and Repair Manual October 2021 102 Power Cable Wiring Diagram from SN Z3414 9686 ...
Page 115: ...October 2021 Service and Repair Manual 103 Drive Contactor Panel Wiring Diagram ...
Page 118: ...Service and Repair Manual October 2021 106 Manifold and Limit Switch Wiring Diagram ...
Page 119: ...October 2021 Service and Repair Manual 107 LVI BCI Option Wiring Diagram ...
Page 122: ...Service and Repair Manual October 2021 110 Charger Interlock Option ...
Page 123: ...October 2021 Service and Repair Manual 111 Engine Wiring Diagram ...
Page 126: ...Service and Repair Manual October 2021 114 Contact Alarm Option from SN Z34F 12066 ...
Page 127: ...October 2021 Service and Repair Manual 115 Fuel Level Sensor Option from SN Z34F 12066 ...
Page 129: ...October 2021 Service and Repair Manual 117 Hydraulic Schematic ...
Page 131: ......