12
20kVA Long Backup Type
250*760*700mm
33kg
20kVA Standard Backup Type
250*680*560mm
145kg(40PCS 9AH Batteries Included
)
30kVA Long Backup Type
250*800*650mm
42kg
30kVA Standard Backup Type
250*800*930mm
215kg(60PCS 9AH Batteries Included
)
3.1.4 Installation Tools
DANGER
To ensure safety, installation tools for live operation shall be insulated.
Installation tools which may be used in installation process are shown in Table 3-2
and used as needed.
Table 3-2 Installation tools
Tool name
Main function
Tool name
Main function
Forklift
Handling
Nail hammer
Knock, install and remove
components
Herringbone
ladder
High-place operation
Rubber hammer
Knock
and
install
components
Clip-on ammeter
Detect current
Percussion drill, drill bit Drill
Multimeter
Check electrical connection
and electrical parameters
Insulating tape
Electrical insulation
Cross screwdriver Fasten screw
Heat-shrinkable tubing Electrical insulation
Leveling
instrument
Leveling
Heat gun
Heat heat-shrinkable tubing
Insulated monkey
wrench
Tighten and loosen bolts
Electrician's knife
Wire stripping
Insulated
torque
wrench
Tighten and loosen bolts
Cable tie
Bundle
Crimping pliers
Cc cold-pressed terminal
Leather working gloves Protect operator’s hands
Hydraulic clamp
Clamp OT terminal
Antistatic gloves
Anti-static
Diagonal pliers
Shear cables
Insulating gloves
Insulation
Wire stripper
Wire stripping
Insulated
protective
shoes
Protect operator
3.2 Unloading and Unpacking
3.2.1 Moving and Unpacking of the Cabinet
The steps to move and unpack the cabinet are as follows
:
1. Check if any damages to the packing. (If any, contact to the carrier)
2. Transport the equipment to the designated site by forklift.
3. Unpack the package.
4. Remove the protective foam around the cabinet.
5. Check the UPS.
(a) Visually examine if there are any damages to UPS during transportation. If any,
contact to the carrier.
(b) Check the UPS with the list of the goods. If any items are not included in the
list, contact to our company or the local office.
6. Dismantle the bolt that connects the cabinet and wooden pallet after disassembly.
Summary of Contents for TEOS+ 300 Series
Page 1: ...TEOS 300 SERIES 10 15 20 30 kVA 3 Phase In 3 Phase Out USER MANUAL...
Page 2: ......
Page 4: ......
Page 62: ......
Page 63: ...AGKK14730 06 2022...