Rev.2.1 08/03/04
7
Refer to Figure 4 before proceeding.
5. Remove junction box cover.
a. Relay Terminals - Connect alarm relays (NO or NC) as required.
Remove Alarm Set point Jumpers from all active channels and JP-9 (If Optional Audible
Alarm and/or Strobe are supplied.) before continuing set-up.
6. Calibrate with a digital VOM as follows:
a. Remove cover(s) on IR Sensor Module(s). Move Jumper(s) from RUN to SETUP (See
Figure 7).
Wait approximately 1 minute before proceeding.
b. Remove lower cover and faceplate on
t
he Haloguard
II/IR Controller
.
c. With VOM on 5 VDC scale, place probes on T2 - SIG (+) and T3 -GND (-) (See Figure 3 -
Controller Lower Circuit Board).
Select MAN mode with push-button, sequence to first channel.
Adjust potentiometer to
the left of each screw terminal with screwdriver until it reads 4.975 VDC.
THIS SET-UP MUST BE COMPLETED FOR EACH IR MODULE
(1 thru 6)
Sequence to subsequent active channels using MAN push button and follow same procedure
for each IR module.
Haloguard
II/IR Controller automatically returns to scanning mode after 2 minutes or press
TEST button to start scanning.
d. Replace IR Module jumper(s) in “RUN” mode.
e. Replace Audible Alarm jumper JP-9 in Haloguard
II/IR Controller, to re-activate audible
alarm circuit.
7. Alarm Set point Adjustment - (See Figure 3 - Lower Circuit Board) Place jumper on appropriate
alarm point to initiate visual or audible alarms and relays.
Lower Circuit Board
IR Module Run/
Setup Jumper
Run
Setup
DO NOT
ADJUST
POTS
Figure 7 - IR Module Circuit Board
Connection for Digital
Calibrator (Optional)
White
Black
Red
Cable to Controller
(DO NOT REMOVE)
B G W R