VOLTMAX ELECTRIC BOILER Installation and Operation Manual
(
Revised June 2017)
, Page
65.
7) When the boiler capacity has reached 100%
as displayed on the controller, measure the
amperage and voltage values drawn by the
unit. These values shall be close to those
shown on the boiler name plate.
8) Slow down the heat demand from the heating
system. The boiler temperature shall
gradually increase and the boiler capacity
shall drop gradually and stabilize when the
boiler temperature will reach a temperature
near the target temperature.
9) When the heating request is completed, the
circulating pump can continue to operate
(depending on the operating mode or the
purge time) or switch off. The heating
elements stop working.
10) Check the operation of the adjustable high-
limit mechanical control.
11) Check the operation of the Low Water Cut
OFF by pressing its test button during 5 sec.