29
7) Installation of hub on the tripod turnstile (Through the example of the turnstile AUIA.095-10
"CENTURION-M"). (
For the sake of convenience installation of the hub with barrier rods is
acceptable at the end of installation and connection of the turnstile):
a) The hub (1) barrier rods
(2)
to be set out manually (
See Fig. 14
).
b) The hub (
1)
to be mounted on center of the turnstile mechanism
(4)
;
During installation attention to be paid that the mechanism fixation holes to be aligned with
the hub holes;
c) The hub
(1)
to be secured with three screws
(3).
Fig. 14
– Installation of the hub with barrier rods into the tripod turnstile body
WARNING:
Legend:
1. Hub;
2. Barrier rods;
3. Allen screws M10x60;
4. Control mechanism (servomotor);
The turnstile is fixed by means of Redibolt anchors (with jacket and screw)
included in the scope of delivery.
The turnstile installation and fixation to be performed only after all
electric cables are pulled.