2. Connection of Boom Barrier and putting it into operation 

 

In further description of Boom Barrier

 

connection to control unit and other devices, connection and wiring 

diagrams the maximum configuration of accessories and options are specified. 

When  in  particular  separate  configuration  some  components  are  not  used,  then  they  just  are  not 

connected or not taken into account. 

The additional options 

are as follows: 

-

 

Heating with heating thermostat. 

It

 

is used in case of frost.

  

-

 

Cooling fan with

 

cooling thermostat. 

It

 

is used in case of hot at the installation site. 

-

 

Audible alarm. 

It

 

is an additional option to  be installed on the Boom Barrier. 

-

 

Radio  controller  of  wireless  remote  control. 

It

 

is  an  additional  option  to  be  used  for  road 

blocker wireless control from remote control panels (remote control pendants). 

-

 

Induction  loop  controllers. 

It

 

is  an  additional  option  to  be  used  for  connection  of  induction 

loops to prevent the Boom Barrier raising when a vehicle is under boom. 

All  optional  device  of  control  units  and  Boom  Barrier  which  can  be  unused  and  are  options  are 

marked with 

"*" 

on diagrams. 

Limit switches

 are used as the Boom Barrier

s ’ 

up and down position sensors. 

2.1. Connection of Boom Barrier and putting them into operation 

 

After  the  Boom  Barrier  installation  the  control  unit  is  connected 

230VAC 

power  supply  network  via 

safety switch 

B6.  Circuit  Breaker 

placed in convenient location. 

The differential breaker 

10А 30мА 

to be used as switch (overload and leakage protection), such as 

ABB 

DS951 C10-30MA/AC

Control  signals  (for  example, access  control  system),  remote  control  panel  B4-

А1. Remote Control Unit 

PCB111  (optional),  emergency  "Stop"  button  B5-

А1

,  Remote  Emergency  Push  Button  "Stop"  ASCO  XAL-

J174 and actuating devices, for example, 

traffic lights, external siren

 are connected to control unit. 

General connection diagram of the Boom Barrier and  additional  devices  is shown in 

Annex 1

Wiring  diagram  of  the  Boom Barrier with  control  unit  and  additional  devices  is shown in 

Annex 2

The switch 

B6-K1. Circuit Breaker, 

the  emergency  stop  button 

B5-

А1.

  Remote  Emergency  Push 

Button  "Stop" 

to  be connected to  the control unit. The  wire remote  control  panel 

B4-

А1.

  Remote  Control 

Unit  RB111

1

 

and  other  additional  devices,  such  as 

traffic  lights 

or 

access  control  system

,  can  be 

connected. 

The emergency stop button 

B5-

А1. Remote Emergency Push Button "Stop" 

and remote control panel 

B4-

А1. Remote Control Unit 

RB111* 

are installed at the road blocker operator workstation.  

The  supply  voltage 

230VAC 

to  be  connected  and  the  switch 

B6.  Circuit  Breaker 

to  be  ON  after 

completion of the Boom Barrier installation, boom balancing and all connections. 

Trial  raising  and  lowering  of  Boom  Barrier  to  be  initiated  after  completion  of  all  connections  and 

energization. Proper operation to be controlled. If the Boom Barrier operation is improper, then the cause to be 
found and the problem to be remedied using 

Table 12

.  

The  Boom  Barrier  has  an  automatic  boom  raising  function,  when  it  does  not  reach  the  down  position 

during lowering (comes up against obstacle, down position sensor is not actuated). 

The automatic boom raising function during coming up against obstacle is activated with the switch 

SW1

The Boom Barrier has a boom deceleration function upon completion of opening or closing. 
The deceleration function is activated with the switch 

SW2

The 

SW3

 switch position determines the deceleration duration during raising. When it is ON  - 1 second, 

when it is OFF- 2 seconds. 

The 

SW4

 switch position determines the deceleration duration during lowering. When it is ON - 1 second, 

when it is OFF- 2 seconds. 

                                                           

1

 

The differential breaker 

10А 30мА 

to be used as switch (overload and leakage protection), such as 

ABB DS951 C10-

30MA/AC

.

 

Summary of Contents for Optimus RB392 Series

Page 1: ......

Page 2: ...eration 13 2 2 Troubleshooting 15 3 1 Wire remote control panel RB111 16 3 2 Boom Barrier wireless control 17 3 3 Protective induction loops 18 4 Road Blocker operator s guide 21 5 Boom Barrier electr...

Page 3: ...control unit is a controller with additional electric parts and is designed to control the Boom Barrier The control unit is assembled in a plastic box and is located inside the Boom Barrier rack Powe...

Page 4: ...4 1 2 Description of the versatile controller PCB349 Fig 2 Illustration of controller PCB349 with identification of its components inputs and outputs...

Page 5: ...inal block for connection of the Road Blocker 1 control inputs sensors and additional devices 9 Terminal block X6 OUT1 Outputs 1 Terminal block for connection of the Road Blocker 1 actuating devices a...

Page 6: ...onnection of neutral N of the Road Blocker1 motor 10 MOTOR 1 PE Output for connection of protective earthing PE of the Road Blocker1 motor When the road blockers are used with peripheral hydraulic uni...

Page 7: ...of DOWN position sensor The Road Blocker will stop when it is activated during lowering When the input is active then it will not respond to lowering command 23 INP SENSOR 3 1 Input for connection of...

Page 8: ...d during lowering When the input is active then it will not respond to lowering command 53 INP SENSOR 3 2 Input for connection of pressure valve It is used only in the road blockers with accumulator 5...

Page 9: ...th accumulator 36 INDICATION LED 1 Output for connection of the Road Blocker 1 additional LED 1 display module anode 37 INDICATION LED 1 Output for connection of the Road Blocker1 additional LED 1 dis...

Page 10: ...r voltage of remote control panel DI 601 39 RS485 A1 Signal RS485 A of angular position sensors DI 601 40 RS485 B1 Signal RS485 B of angular position sensors DI 601 41 GND Common wire GND of angular p...

Page 11: ...sensors induction loops or safety photocells 25 26 55 56 INP Safety When the switch is OFF then road blocker will be stopped when signal is coming on INP Safety When the switch is ON then road blocker...

Page 12: ...econds selected by the TIME1 after each raise or lower command and will stop after this timeout has been completed The timeout of raising and lowering increases when the regulators is rotate clockwise...

Page 13: ...lights external siren are connected to control unit General connection diagram of the Boom Barrier and additional devices is shown in Annex 1 Wiring diagram of the Boom Barrier with control unit and a...

Page 14: ...lowering are determined by the of the position sensors position limit switches and magnets If appropriate end position sensors to be adjusted according to the diagram shown in Fig 5 Fig 5 Adjustment...

Page 15: ...well as errors to be eliminated and connection to be made properly 2 Continuous operation of motor after reaching UP and DOWN position by Boom Barrier End position sensors Sensor TOP or Sensor BOT ar...

Page 16: ...ar DOWN button will be blinking during lowering When Road blocker reaches the lowermost position and stops then the lamp near DOWN button will be steadily lit DOWN position display Road blocker is sto...

Page 17: ...pendant Satel T 2 to be pushed to raise the road blocker Red DOWN button of remote control pendant Satel T 2 to be pushed to sink the road blocker To add new remote control pendants Satel T 2 in stor...

Page 18: ...for preparation of induction loops The maximum allowable distance from induction loop to control unit is 20 m Induction loop responds to vehicle metal and at its location there should not be metal in...

Page 19: ...20 6 10m 3 3 2 0 975m 4 1 22m 22 6 71m 3 3 2 0 975m 4 1 22m 24 7 32m 3 3 2 0 975m 4 1 22m 26 7 93m 3 3 2 0 975m 4 1 22m 28 8 54m 3 3 2 0 975m 4 1 22m 30 9 14m 2 3 2 0 975m 4 1 22m 32 9 75m 2 3 2 0 97...

Page 20: ...s of cable SIF1 0 of each induction loop to be connected to terminals LOOP and LOOP of Safety Loop Detector EMX ULTRADIN induction loop controller of control unit Fig 11 Diagram of connection of induc...

Page 21: ...dependent road blockers connected to one control unit The Road Blocker wireless control pendant Satel RE 2K is equipped only with buttons UP and DOWN but is not equipped with button STOP The operator...

Page 22: ...rgency stop button Emergency Stop When this button is pushed then the Boom Barrier will be stopped and will be standstill until it is released and new commands UP or DOWN are generated When the button...

Page 23: ...damages of the Boom Barrier to be visually inspected Integrity of circuit of protective earthing P of Boom Barrier metal parts with circuit of earthing P of power supply network earthing circuit resis...

Page 24: ...X5081 03PFS 5 08 mm 3 pin 1 12 NX5081 TF Pin for 5 08mm Connector 6 13 Connector WAGO 264 336 1 14 Connector WAGO 264 354 1 15 Connector WAGO 264 357 1 16 Connector WAGO 264 361 1 17 Thermostat KSD970...