1.2.2 Mounting the UMAP 2110
The position and orientation of the brackets depends on the rack used for mounting. The DSLAM
can be front-mounted in a standard channel rack (5-inch projection); and it can be shipped with the
mounting brackets installed in one of three mounting positions or shipped loose (see Figure 1-2).
The mounting brackets can be rotated for use in wall mounting. Optional adhesive feet may be
attached to the bottom of the chassis so that it can be placed on a desk or other smooth surface.
STANDARD
FRONT MOUNT
FRONT
MOUNTING
BRACKET
MOUNTING
BRACKET
Figure 1-2 Mounting Bracket Orientation (Top View)
After the site requirements have been verified, the chassis may be installed at the specified location.
When mounting the chassis, practice good safety habits. Use two or more people to secure the
chassis. Relay rack mounting normally requires at least two people.
Step Action
1
Locate the chassis and obtain the appropriate chassis mounting hardware.
2
Determine and obtain the tools required for the chassis mounting hardware.
3
From the front of the relay rack, position the chassis in its relay rack mounting location.
4
Using the appropriate rack mounting hardware, secure the chassis in its relay location on
both left and right side of mounting bracket (see Figure 1-3).
Note —
The chassis should be empty during the chassis mounting procedures. Remove any unit in
the chassis, and store them according to static-sensitive device storage procedures.
Warning —
Hazardous voltages may exist on the chassis. Always practice good safety habits
when wiring a live circuit or performing maintenance.
6 / 54
Summary of Contents for UMAP 2110
Page 2: ......
Page 10: ...2 54 ...
Page 28: ...1 Installation of the UMAP 2110 20 54 ...
Page 33: ...1 Installation of the UMAP 2110 Fail to Get File 25 54 ...
Page 43: ...1 Installation of the UMAP 2110 35 54 ...
Page 44: ...1 Installation of the UMAP 2110 36 54 ...
Page 60: ...52 54 ...
Page 61: ...53 54 ...
Page 62: ......