Shift protection on the machine base frame
65
TK Elevator
BA, TW45C | 6231003860 | 06/2022
2. Set the distance between the rope and rope guard to a maximum of 2
mm by swivelling and/or re-mounting.
3. Set the rope guard with a maximum angle of 15° at the rope entry point
and rope departure point.
Make sure that there is a maximum of 90° between the rope guards.
4. After alignment, tighten the securing bolts of the rope guards with the
prescribed tightening torque.
6.5
Shift protection on the machine base frame
The fastening materials (Hilti HST M16/25 or Fischer M16/25 FAZ II) are in-
cluded in the scope of supply and must be attached to the unfinished floor.
Comply with the installation instructions of the manufacturer.
i
In locations where the distance to the wall is < 250 mm, the standard shift pro-
tection devices must be replaced by devices for low wall clearances.
The shift protection is configured for the following machine insulations:
▪
Insulation elements without underlay for machine room without floor
pavement
▪
Insulation elements with underlay for machine room with floor pavement
(≤ 60 mm height); support made from Multiplex laminated wood
140x140x80 mm.
4
4
4
3
2
1
4
4
4
3
2
1
max. 5 mm
Fig. 35
ATR_2_00_0002_0
Item Designation
Item Designation
1
Shift protection
2
Machine base frame
3
Anchoring device
4
Alternative holes
1. Position the shift protection elements contact-free with a slight clearance
(maximum 5 mm) to the machine base frame and make marks.