6. Raise the lift off the safety locks by pressing the
push button on the power unit. Make sure you raise
the lift by at least two inches to allow adequate
clearance for the safety lock to clear. ( See Fig. 8.3 -
8.5)
STEP 9
(Bleeding)
1.
Lift must be fully lowered before changing or adding
fluid.
2.
Raise and lower lift six times. The cylinder is self
bleeding. After bleeding system, fluid level in power unit
reservoir may be down. Add more fluid if necessary to
raise lift to full height. It is only necessary to add fluid to
raise lift to full height.
3.
To pressure test, run lift to full rise and run motor for
approximately 3-seconds after lift stops. This will place
pressure on the hydraulic system. Stop and check all
fittings and hose connections. Tighten or reseal if
required.
POST-INSTALLATION CHECK-OFF
8.
Lower lift by depressing lowering valve on
power unit.
9.
Run the lift up and down a few times to ensure that
the locks are engaging uniformly and that the safety
release mechanisms are functioning. Re-adjust if
necessary
Lift Assembly, Level And Stable
Arm Assemblies Properly Attached
Electric Power Supply Confirmed
Safety Locks Functioning Properly
Check For Hydraulic Leaks
Oil Level
Lubrication of Critical Components
Check For Overhead Obstructions
Runways Level
All Screws, Bolts, and Pins Secured
Surrounding Area Clean
Operation, Maintenance and Safety Manuals on Site
Fig. 8.3
Safety Unlocked
Fig. 8.5
Fig. 8.4
Safety Pin
Safety
Blocks
Safety Unlocked