Table 7 Possible problems during the operation
6.THE FIRST COMMISSIONING
The boiler should be put into operation by a qualified person. If unqualified person performs the
putting into operation, there is the possibility of damage and complete destruction of the boiler.
Improper handling can cause injuries.
6.1. Requirements for successful
commissioning
The following conditions must be met before starting safe putting into operation of the boiler:
TURN
OFF THE ELECTRICAL SUPPLY TO THE BOILER
Is the main swath for power supply to boiler turned off?
CHECK MECHANICAL COMPONENTS OF THE BOILER
Are all mechanical components properly implemented into the boiler?
Are all mechanical components properly and firmly fixed to each other?
CHECKING OF PIPING AND INSTALLED COMPONENTS
Is the circulation pump properly implemented?
Is the safety valve properly implemented?
Danger!
Risk of electric shock during the connection to circulating pump to electric network.