18
2 - Operation and maintenance
TO320 M - EN - Ed. 04.09
Pneumatic VDC
11.2.3
In the pneumatic VDC the work sequence is preset by the user to control the opening/closing times
of both flaps.
Torex recommends a 10 cycles/minute work sequence.
The user must make the solenoid valve connections in the terminal board present onboard the ma-
chine.
Upper flap opening - closure:
power terminal 8 to allow extension of the lower cylinder thereby
opening the upper flap. Disconnect the power supply to terminal 8 and the cylinder returns to the
retracted position, thereby closing the upper flap.
Lower flap opening - closure:
power terminal 6 to allow extension of the upper cylinder thereby
opening the lower flap. Disconnect the power supply to terminal 6 and the cylinder returns to the
retracted position, thereby closing the lower flap.
Use of a control panel is recommended for control of the working cycle!
Summary of Contents for VDC 200
Page 1: ...VDC Double dump valve EN TO320 EN Ed 04 09 ...
Page 7: ...TECHNICAL CATALOGUE TO320 T EN Ed 04 09 1 VDC Double dump valve EN ...
Page 24: ......
Page 25: ...VDC Double dump valve EN OPERATION AND MAINTENANCE TO320 M EN Ed 04 09 2 ...
Page 66: ......
Page 67: ...SPARE PARTS CATALOGUE VDC Double dump valve EN TO320 R EN Ed 04 09 3 ...
Page 76: ...10 3 Spare Parts Catalogue TO320 R EN Ed 04 09 Plate 2 Counterweight 2 1 2 4 2 3 5 ...