4.1.2 Power Connection Cable Routing
The following illustrates the proper cable routing that should be followed during the
power connection process of the 75 and 100kVA.
Note:
1) Input and Output conductors shall be installed in separate conduits, and installed in
accordance with the latest edition of NEC and the authority having jurisdiction.
2) Battery conductors shall be installed in a separate conduit and be of low resistance type.
Top Conduit Entry
Main Input
Main MCCB
Main Input (N)
Output
Ground
Bottom Conduit Entry