RECEIVING, INSPECTION AND HANDLING
Page 9
RECEIVING AND UNPACKING
The circuit breaker units are subjected to factory
production testing prior to being packed and
shipped.
ACCEPTANCE INSPECTION
Confirm that the circuit breaker unit is complete,
correct as specified and undamaged from
shipment and handling.
Upon receipt of the equipment, do the following:
1) Make an immediate inspection for damage
which might have occurred during shipment.
If damage is discovered, it should be noted
with the carrier prior to accepting the
shipment, if possible.
2) Carefully unpack the equipment sufficiently to
check for missing parts or concealed
damage.
3) Check for the presence of accessories that
are shipped with the circuit breaker:
-
Closing Handle (shipped loose with
MU and ML type breakers) (Fig. 4)
-
Insulating cylinders (qty-6) (Fig. 5)
3) Keep the circuit breaker upright.
Never lay the circuit
breaker on its side or
upside down. This may
cause damage.
4) File a claim with the carrier for any damaged
or missing items and immediately notify the
nearest Toshiba representative.
Do not install or energize
equipment that has been
damaged. Damaged
equipment can fail during
operation, resulting in fire
and explosion.
Fig. 4 Closing Handle
Fig. 5 Insulating Cylinder
CAUTION
WARNING