104
15
Backup Operation
Emergency Operation
Outdoor backup setup in cooling season (Simple setting method)
Outline
When either inverter unit or fixed-speed unit fails during cooling season, this function is used to
perform emergency operation quickly.
When the interface or electric circuit system fails, emergency operation by this setup
cannot be performed.
In this case, refer to “When outdoor unit has failed” section.
Work procedure
(1) First,
turn off the source power of all the outdoor units
which are connected to
the system.
(2) The following works are performed to the
failed outdoor unit
.
(Even if the failed outdoor unit is the inverter unit or fixed-speed unit, the following works
are common specifications.)
1) Set
DIP SW06/Bit 1 and Bit 2 on the interface P.C. board to ON
.
2) If refrigerant leakage occurred on PMVB, close the service valve of the liquid
pipe fully. (Fully close by turning clockwise)
(3)
Turn on source power of each outdoor unit.
If the fault is a compressor insulation error, etc., disconnect the lead wire of the compressor
previously before work.
(4) Emergency process is complete. The operation then starts by a command from the
indoor unit.
Summary of Contents for MM-A0160HX
Page 1: ...Service Manual Air Conditioner Multi Split Type System Modular Multi System HFCR407C A90 0130 ...
Page 2: ......
Page 133: ...134 20 Additional Literature and Contacts ...
Page 134: ...135 20 Additional Literature and Contacts ...
Page 135: ...TOSHIBA AIR CONDITIONING www toshiba aircon co uk MADE IN UK A90 0130 Revised April 2001 ...