Read this section completely before attempting to install, or operate the equipment.
5.1
Delivery and Uncrating of Unit
Inspect equipment and shipping crate immediately upon receipt. If any damage is apparent, you should
discuss it with the trucking delivery person and contact the transportation company immediately. Make notes
of any damage on the Bill Of Lading. Retain all shipping materials for inspection. Any claims for damage
must start at the receiving point. Check packing slip carefully and make sure all materials have been
received as indicated on the packing ticket. Unless otherwise noted, YOUR ORDER HAS BEEN SHIPPED
COMPLETE.
Chambers and any remote machinery skids or control cabinets should be handled and
transported in an upright position. They must never be carried on their back, front, or any side.
Important!
Due to the vibration incurred during shipping and handling, it is possible that mechanical
connections could become loose. Check all connections to make sure they are secure.
5.2
Location and Installation of Unit
Classification: NFPA 86 Class B ovens are heat utilization equipment operating at approximately
atmospheric pressure wherein there are no flammable volatiles or combustible material being heated in
the oven.
Do not place the unit near combustible materials or hazardous fumes or vapors.
Do not locate unit in areas of wide ambient temperature variation such as near vents or outdoor
entrances.
Do not install unit in a corrosive environment. A corrosive environment may lead to poor performance
and deterioration of unit.
Ventilation: The oven should be installed in an area where there is good air ventilation. Allow a
minimum of 5 inches between any wall and any oven side.
Do not position the oven in a manner that would make it difficult to operate your main power
disconnect switch.
Make sure the oven is leveled when set up. The floor of the chamber should be leveled with a Spirit
Level to +/- 1/8” (3.175 mm) front to back and side to side.
Floor stands may be provided as an option.
Stacking frames may be provided to securely stack units on top of one another.
Very Important!
Upon completion of the initial installation of the chamber and upon completion of any
maintenance procedure, make sure that all access panels that have been removed are reinstalled securely
before operating the unit.