7 Checklist, Part 1 of 2
We recommend that you print out and work through the checklist for commissioning, replacing the
measuring system and when changing the parameterization of a previously accepted system and
store it as part of the overall system documentation.
Documentation reason
Date
edited
checked
Sub-item
Note
Reference
yes
This Safety Manual was read and
understood
–
Document no.: TR-ECE-BA-GB-0142
Interface-specific User Manual
●
Go through and use the checklist
part 2 of 2
See Chapter Document Download on
Verify that the measuring system can
be used for the present automation
task based on the specified safety
requirements
●
Intended use
●
Compliance with all technical data
●
Chapter
●
Chapter
-> Product data sheets, Page 29
●
Interface-specific User Manual
(Checklist, part 2 of 2)
Meeting the assembly requirements
defined in the Safety Manual
●
Safe mechanical attachment of the
measuring system and safe form-
locking connection of the driving
shaft to the measuring system
●
Chapter
Supply voltage
●
The power supply unit used must
meet the requirements of
●
Chapter
-> Product data sheets, Page 29
●
Interface-specific User Manual
(Checklist, part 2 of 2)
Proper
– electrical installation (shielding)
– Network installation
●
Comply with general installation
rules
●
Comply with wiring standards
●
Comply with the guidelines provided
by the relevant field bus user
organizations
●
Interface-specific User Manual
(Checklist, part 2 of 2)
After commissioning and parameter
changes
– System test
– Validation (Settings – Axis)
●
During commissioning and whenever
parameters have been changed
– all relevant safety functions
involved must be checked
– if several (similar) axes are used,
make sure that the settings have
been made for the desired axis
●
Interface-specific User Manual
(Checklist, part 2 of 2)