Installer’s Guide
SUPPLEMENTARY HEATERS CHECKOUT PROCEDURES
IF A HEATER IS USED, SEE "INSTALLATION LIMITATIONS & RECOMMENDATIONS"
TO DETERMINE IF THE HEATER REQUIRES A SPECIAL CIRCUIT.
1. Be sure the disconnect switch is OFF, and safety label (if any) is attached ................................. [ ]
2. Check field wiring for tight connections and grounding according to codes ................................. [ ]
3. Check circuit protection for proper size per nameplate specifications .......................................... [ ]
4. Check control box panel — in place and secured ........................................................................... [ ]
NOTE: Operation of heaters must be checked during the operation check of the total system.
CHECKOUT PROCEDURES
After installation has been completed, it is recommended that the Air Handler be checked against the following
checklist.
1. Make sure power is OFF at power
disconnect switch ..................................................... [ ]
2. Check all field wiring for tight connections. See that
grounding of unit is in accord with code ................. [ ]
3. Make sure unit suspension (if used) is secure and
that there are no tools or loose debris in, around or on
top of the unit ........................................................... [ ]
4. Check all duct outlets; they must be open and unre-
stricted ...................................................................... [ ]
5. Check drain lines and be sure all joints are
tight .......................................................................... [ ]
6. Make sure secondary drain pan is installed ........ [ ]
7. Check power supply for correct requirements per
unit nameplate ......................................................... [ ]
8. Check filters for proper size. Inform owner of proper
procedure for removal and reinstallation ............... [ ]
9. Energize the system and carefully observe its opera-
tion; make any necessary adjustment .................... [ ]
10. Instruct owner, engineer (if applicable) on proper
operating procedure and leave Use and Care Manual
with owner ................................................................ [ ]
O. CHECKOUT PROCEDURE
1.
Check the Air Handler installation in accordance
with the instructions below.
2.
“Operational Procedure” for the system installation
can be found in the outdoor unit Installer Guide and
will be compatible with this Air Handler.
Trane
6200 Troup Highway
Tyler, TX 75707
05/10
The manufacturer has a policy of continuous product and product data improvement, and it reserves the
right to change design and specifications without notice.