32
18-CD29D1-3
Installer’s Guide
TABLE 15
NATURAL GAS ONLY
TABLE OF CUBIC FEET PER HOUR OF GAS
FOR VARIOUS PIPE SIZES AND LENGTHS
PIPE
SIZE
LENGTH OF PIPE
10
20
30
40
50
60
70
1/2
132
92
73
63
56
50
46
3/4
278
190
152
130
115
105
96
1
520
350
285
245
215
195
180
1-1/4
1050
730
590
520
440
400
370
This table is based on pressure drop of 0.3 inch W.C. and 0.6 SP.GR. gas
TABLE 16
ORIFICE SIZES
MODEL
INPUT
RATING
BTUH
NUMBER
OF
BURNERS
MAIN BURNER ORIFICE
DRILL SIZE
NAT. GAS
LP GAS
*UH1B040A9241A
40,000
2
45
56
*UH1B060A9361A
60,000
3
45
56
*UH1B080A9421A
*UH1C080A9601A
80,000
4
45
56
*UH1C100A9481A
*UH1D100A9601A
100,000
5
45
56
*UH1D120A9601A
110,000
6
45
56
*DH1B040A9241A
40,000
2
45
56
*DH1B065A9421A
60,000
4
48
56
*DH1C085A9481A
80,000
5
48
56
*DH1D110A9601A
110,000
6
48
56
COMBUSTION AND INPUT CHECK
1. Make sure all gas appliances are off except the fur-
nace.
2. Clock the gas meter with the furnace operating (de-
termine the dial rating of the meter) for one revolu-
tion.
3. Match the “Sec” column in the gas flow (in cfh)
Table 18 with the time clocked.
4. Read the “Flow” column opposite the number of sec-
onds clocked.
5. Use the following factors if necessary:
For 1 Cu. Ft. Dial Gas Flow CFH =
Chart Flow Reading ÷2
For 1/2 Cu Ft. Dial Gas Flow CFH =
Chart Flow Reading ÷4
For 5 Cu. Ft. Dial Gas Flow CFH =
10X Chart Flow Reading ÷4
6. Multiply the final figure by the heating value of the
gas obtained from the utility company and compare
to the nameplate rating. This must not exceed the
nameplate rating.
Gas Valve Adjustment
Changes can be made by adjusting the manifold pres-
sure (See Table 17, or changing orifices (orifice
change may not always be required). To adjust the
manifold pressure:
1. Turn off all electrical power to the system.
2. Attach a manifold pressure gauge with flexible
tubing to the outlet pressure boss marked “OUT P”
on White-Rodgers gas valve model 36G or 36J. See
Figure 58 for White-Rodgers gas valve model 36J.
See Figure 57 for White-Rodgers gas valve model
36G.
3. Loosen (Do Not remove) the pressure tap test set
screw one turn with 3/32" hex wrench.
a. The pressure tap adjustment kit (KIT07611)
contains a 3/32" hex wrench, a 5/16" hose and a
connector and can be ordered through Global
Parts.
4. Turn on system power and energize valve.
HORIZONTAL FURNACE GAS PIPING MAY BE FROM EITHER SIDE (UPFLOW SHOWN)
GROUND UNION JOINT
DRIP
LEG
AUTOMATIC GAS VALVE
WITH MANUAL SHUTOFF
MAIN MANUAL
SHUTOFF VALVE
GROUND
UNION JOINT
DRIP
LEG
MAIN MANUAL
SHUTOFF VALVE
AUTOMATIC GAS VALVE
WITH MANUAL SHUTOFF
R