Installation - Mechanical
CLCH-SVX013B-EN
25
to be connected to the air handler by the installing
contractor. See
.
Note:
It is required that the hoods be sealed to the unit
using factory-provided butyl/caulk tape.
Figure 30.
Hood installation
AHU outdoor roof
Butyl caulk tape
1.00 W x .125T
Hood
Nut-Hex .31-18
Detail A
Screw self-driller
10-16 x .750
or
1/4-in. x .750
Butyl caulk tape
1.00 W x .125T
Nut-Hex .31-18
Bolt
0.313-18 x .750 Hex
Bracket Support
Angle Hood Support
(when required)
Bolt .313-18 x .750 Hex
Bracket support
Stacked Outdoor Unit Assembly
Assembly Hardware
Table 6.
Parts list for outdoor stacked units
Item
Description
Item
Description
1
Gasket: 1.00T x 4.00W
9
Guard: perpendicular to airflow flashing
2
Bracket: Stacked unit
12
Guard: Direction of airflow flashing
3
Screw: 0.313-18 x 0.875 sheet metal
13
Guard: Flashing seam cover
4
Screw: 10-16 x 0.750 self driller
14
Adhesive/sealant: Flex polyurethane
5
Tape: Butyl 0.38T
15
Bracket: Hood support
6
Tape: Ribbed Butyl
16
Angle: Hood support
7
Plate: Vertical seam cap
17
Screw: 0.250-14 x 0.750 self driller
8
Tape: 0.12T x 1.00W, gray Butyl
Unit Assembly
1. See
. Apply gasket (Item 1) on top of lower
unit. Compress gasketing to ensure a good air seal
between upper and lower sections.
2. Place upper unit on lower unit.
3. Remove lifting lugs from top unit and attach stacking
brackets (Item 2) to top and bottom units using screws
(Item 3 and Item 4). See Detail A in
brackets (Item 2) are to be used on the right and left
sides at each shipping split section end and also on
front and back of the unit.
4. Apply Butyl tape (Item 5) to one side of the shipping
split section.
5. Slide shipping split sections together, pulling tight
using lifting lugs and threaded rod on bottom and
straps or pipe clamps on top.