Installation – FIADMPR102*
ACC-SVN231A-EN
7
Factory Installed Damper Set-Up
Downflow Configuration
To position damper for downflow operation, complete the
following steps:
WARNING
Hazardous Voltage!
Failure to disconnect power before servicing could
result in death or serious injury.
Disconnect all electric power, including remote
disconnects before servicing. Follow proper lockout/
tagout procedures to ensure the power can not be
inadvertently energized. Verify that no power is
present with a voltmeter.
1. Remove filter access panel.
2. Remove bottom blockoff from its shipping location.
Figure 4.
Remove bottom blockoff
3. Remove the bottom three screws from the damper
panel.
4. Pull the damper assembly out into operating position
as shown in
.
5. Secure the damper assembly with two screws at the
bottom of the corner posts.
6. Install bottom blockoff and secure with three screws.
Figure 5.
Damper assembly operating position
Remove screw to
remove bottom
blockoff from
shipping location.
Bottom Blockoff
Screws used to
secure economizer
Bottom Blockoff