9
Locate the boiler in front of the final position before removing
1.
the crate.
Locate the unit so the vent pipe connection to chimney will be
2.
short and direct.
The Boiler is suitable for installati
3.
on on combustible floor. Boiler
cannot be installed on carpeting.
For basement installation, provide a solid elevated base, such as
4.
concrete, if floor is not level, or if water may be encountered on
floor around boiler.
Provide recommended service clearance, if applicable, as
5.
follows:
Clearance from Jacket Front Panel
24” for servicing burner
•
Clearance from Jacket Side Panels
24” for burner swing door, if opened fully with burner mounted,
•
otherwise 2” with burner removed.
Clearance From Jacket Rear Panel
12” minimum for rear smoke box cleaning. (Note: this dimension
•
will also be controlled by horizontal to vertical to horizontal
smoke pipe arrangement. See
Figure #1
.
TABLE 2A: BOILER DIMENSIONS
Section
Height
Depth
Width
4
34 1/4”
17 3/4”
17 3/4”
5
34 1/4”
20 7/8”
17 3/4”
6
34 1/4”
24 1/8”
17 3/4”
7
34 1/4”
27 1/2”
17 3/4”
LOCATiNg THe BOiLer
taBLE 2B: BOiLER cLEaRaNcES
Unit
Combustible Clear-
ance
Accessibility, Cleaning,
and Servicing
Top
12”
24”
Right Side
2”
24”
Left Side
2”
24”
Floor
Combustible
No Requirement
Front
17”
24”
Back
See Flue
18”
All distances measured from the boiler jacket or flue.
For minimum clearances to combustible materials, see
6.
Figure
#1
and
Table 2B
.
Fresh air fo
7.
r combustion and ventilation must be available at the
boiler. Ventilating and combustion air must enter boiler room
without restrictions.
Be sure installation is in accordance with the requirements of
8.
the local authorities having jurisdiction. Compliance with these
regulations is required. In the absence of local codes, in the United
States, follow NFPA 31 Installation of Oil Burning Equipment,
latest revision. In Canada, use CSA B 139, latest revision.
Clearance to venting is for single wall flue pipe. If Type L vent is
9.
used, clearance may be reduced to the minimum required by the
vent pipe manufacturer.
9”
24”
SEE
TABLE
9”
2”
9”
9”
9”
9”
12”
34 1/2”
15”
17 3/4”
COMBUSTIBLE
CONSTRUCTION
NON-COMBUSTIBLE
CONSTRUCTION
See
Table 2A
See
Table 2B
Figure 1 - Clearances to Combustible Construction