Trina Solar User Manual | Vertex Series Modules
17
Use 4 clamps on the short side and 2 clamps on the long
side.
Use 2 clamps on the short side and 2 clamps on the long
side.
Mounting rails run perpendicular to the long side frame.
DE09
DE09.05
DE09.08
A = (0 - 200) mm
B = (0 - 200) mm
Uplift load ≤ 2400 Pa
Downforce load ≤ 3000 Pa
DE09
DE09.05
DE09.08
A = (250 - 450) mm
B = (100 - 250) mm
Uplift load ≤ 1800 Pa
Downforce load ≤ 2400 Pa
DE18M(II)
DE18M.08(II)
A = (0 - 200) mm
B = (0 - 200) mm
Uplift load ≤ 1800 Pa
Downforce load ≤ 1800 Pa
DE18M(II)
DE18M.08(II)
A = (250 - 450) mm
B = (100 - 250) mm
Uplift load ≤ 1000 Pa
Downforce load ≤ 1200 Pa
DEG18MC.20(II)
A = (250 - 450) mm
B = (100 - 250) mm
Uplift load ≤ 1000 Pa
Downforce load ≤ 1300 Pa
Slide-in rails on the short side.
Use 4 clamps on the long side.
Mounting rails run perpendicular to the long side frame.
DE09
DE09.05
DE09.08
Uplift load ≤ 2000 Pa
Downforce load ≤ 2400 Pa
DE09
DE09.05
DE09.08
A = (200 - 250
or 350 - 400) mm
Uplift load ≤ 3000 Pa
Downforce load ≤ 3600 Pa
A = (100 - 200
or 400 -500) mm
Uplift load ≤ 2000 Pa
Downforce load ≤ 2400 Pa
DE18M(II)
DE18M.08(II)
DEG18MC.20(II)
Uplift load ≤ 1000 Pa
Downforce load ≤ 1000 Pa