Unless otherwise specified, the water wash supply
should be hot
(140°F recommended - WATER
HEATER NOT SUPPLIED BY TRION
®
)
at the volume
specified for the given unit, and at a full flow pressure
between 40 and 50 psig measured at header.
Although not required, a pressure gage and a manual
service valve are recommended as shown in the
plumbing schematic (separate from this manual). The
components should be located within the system to
provide for service access.
7. Mount Control Panel
The control panel should be mounted indoors (unless
supplied with a weatherproof enclosure), at eye
level, and located as close to the ESP as practical.
Allow sufficient space in front of the access door(s)
for service. Refer to appropriate control panel outline
drawing for mounting hole layout and dimensions.
8. Complete Wiring
a.
Primary Wiring
: The control panel is the main
distribution point for all primary wiring. The various
electrical components involved are connected to
and powered from the control panel.
b.
Grounding
: An earth ground must be provided
to the Grease Viper cabinet and control panel. All
ground connections must be in contact with bare
metal and securely affixed. Ground conductor size
and connection means will be in accordance with
all applicable electrical code standards.
WARNING
Precautions should be taken in the event the water
supply, detergent piping, and drains are subjected to
freezing temperatures: 1) All plumbing components
– backflow preventer, ‘Y’ strainer, pressure gauge,
solenoid valve(s), detergent system, drain valve,
and air gap fitting - must be installed indoors or
in a heated mechanical room in accordance with
the plumbing schematic to prevent freezing. 2) All
piping exposed to cold climate outdoor conditions
should be heat traced and insulated to prevent
freezing. 3) An air gap fitting should be installed on
the drain line to facilitate gravity draining of wash
water from the internal headers and manifolds.
4) The water supply line should be pitched back
toward the heated space.
9. Check Out for System Start-up
When the installation has been completed, assure
that the equipment is ready for start-up by checking
the following:
• All construction debris has been removed from the
ionizing-collecting cells, drain basin and ductwork.
• The inside of the control panel and detergent tank
are clear of any foreign materials.
• The drain lines from the Grease Viper drain basins
are clear and completely connected to their point
of termination.
• All piping is completed to the manifold headers
and wash water is available.
• Supply line power is available and electrical wiring
is completed to the following components:
a. Control Panel
b. Solenoid Valve(s)
c. Detergent Pump Motor
d. Electrical Interlocks
e. Power Supplies for Ionizing-Collecting Cells
f. Exhaust Fan
FOR THE MAINTENANCE ENGINEER
1. Introduction and Principle of Operation
The TRION
®
electronic air cleaner is technically known
as an Electrostatic Precipitator (ESP). In this type of
equipment, all airborne particles, even of microscopic
size, are electrically charged (positively) as they
pass through a high voltage ionizer. These charged
NOTE
Do not add the initial supply of detergent into the
detergent tank - this is to be done after volume
settings are adjusted at start-up.
Operation & Service
WARNING
RISK OF ELECTRIC SHOCK
These servicing instructions are for use by
qualified personnel only. To reduce the risk of
electric shock, do not perform any servicing other
than that contained in the operating instructions
unless you are qualified to do so.