15
Triple Solar assembly instruction PVT heat pump panels UK January 2021
Figure 7.2-e middle clamp fixed
Figure 7.2-d middle clamp prepared
4.
Grease two connecting hoses with acid-free silicone grease.
Attention:
Use only acid-free silicone grease (or blue gel) that is suitable for EPDM O-rings and
can withstand temperatures between -20°C and +70°C. This is supplied.
5. Slide the two connecting hoses into the headers until both O-rings are no longer visible,
see figure 7.2-c.
Figure 7.2-c
–
connecting hoses, mounted on one side
6. Carefully push the entire panel sideways in one controlled movement to allow the
headers to slide over the connecting hoses.
Attention:
Beware of damaging the connecting hoses and the O-rings. If in doubt, replace!
7. Secure both panels with the TS middle clamp and socket head screw M8x40, see
figures 7.2d and 7.2e . The cutouts on either side of the TS middle clamp must fall over
the ridges of the panels to secure the assembly!