11. Maintenance

The heat pump panels are basically maintenance-free. However, there are a few recommendations in this area:

It is recommended to check the connections annually for fluid tightness and corrosion due to external factors 

such as the weather or other conditions.

In the case of vertical installation (90°) against a facade, it is recommended to clean the heat pump panels 

regularly with water if they are not exposed to rain.

Check the fins on the underside of the heat pump panels annually for leaves or insects to maximize the 

performance of the panels.

In case of a system conversion, it is recommended to replace the new glycol resistant O-rings and/or gaskets at 

the disconnected connection hoses.

If the pipes on the roof have to be closed for maintenance, make sure that the expansion tank of the source 

can remain active. After all, the source can heat up and cause the fluid to expand. Close the filter valve 

(supplied with Nibe heat pumps) and the valve of the flush and fill connection set.

12. Warranty conditions

For our terms and conditions, see www.triplesolar.eu. Points of attention here:  

Warranty conditions products

Triple Solar gives a product warranty on the heat pump panels for a period of 10 years.

PV panels, heat pumps and other components are supplied in accordance with the manufacturer's warranty 

(e.g. Bisol guarantees a 10-year product warranty and a 25-year performance guarantee of >85% of the 

initial capacity).

Product warranty is excluded at:

1.

Damage caused by improper assembly, maintenance or repairs in which non-original parts have been 

used.

2.

Defects caused by improper use or use of products other than those for which they were manufactured 

and intended.

3.

Damage caused by external causes.

4.

Discolouration due to UV radiation and lacquer corrosion.

5.

A removed or illegible type plate.

Entrance control:  

Please check the delivered products for any damage immediately upon delivery. In the case of obvious 

defects or incorrect deliveries, this must be reported to Triple Solar in writing by e-mail to 

order@triplesolar.eu at the latest 2 working days after receipt of the products. Please state your order 

number.

No rights can be derived from the information and instructions in these assembly instructions.

Triple Solar BV

Programmeurstraat 6-B 

1033 MT Amsterdam

Tel +31 (0)20 435 7555

info@triplesolar.eu

www.triplesolar.eu

Summary of Contents for M2 300 165 landscape

Page 1: ...manual heat pump panels triple solar heating without gas...

Page 2: ...gning panels and installing roof brackets 8 6 Preparation for a flat roof 12 7 Installation of the panels 13 Placing the TS clamping profile 13 Mounting of the panels 14 Mounting the TS clamping profi...

Page 3: ...surface during installation Stop the installation in case of strong gusts of wind Provide lightning protection during assembly in accordance with building regulations Legal requirements standards and...

Page 4: ...ion PVT heat pump panels March 2020 2 Technical information Measures Model M2 360 200 landscape Model M2 300 165 landscape Figure 2 1 a heat pump panel type M2 360 200 landscape Figure 2 1 b heat pump...

Page 5: ...8 1 65 materials PV panel Glass Heat exchanger tubes Copper Heat exchanger fins Aluminium Finishing Kataforese 3 Placement of the panel field Inclination angle on flat roof Mount heat pump panels at a...

Page 6: ...ption Specification Image 322101 324201 Mounting rail 2120 mm 4200 mm 330101 Mounting rail connector Aluminium with M8 flange nuts 310300 TS clamping profile slide connector Assembly of plastic and st...

Page 7: ...dditional components required for flat roof installation Art nr Description Specification Aantal Image 300510 Flat roof frames first panel south per row Sunbeam Universal 1x per panel Zie figure 4 3 a...

Page 8: ...d fill connection set 1 inside DN25 500100 Expansion vessel 18 L 500150 Expansion vessel connection group Including automatic air vent pressure gauge and pressure relief valve 3 bar 800010 TS crane gr...

Page 9: ...ting the installation Four roof brackets are required per panel 2 Screws are included per roof bracket 7 0x50 stainless steel Attention The dimensions in figure 5 1 a are critical If they are not resp...

Page 10: ...p panels March 2020 Figure 5 1 b Pitched roof alignment diagram dimensions in mm The lengths can differ per type of panel Attach the roof brackets if necessary with extra underlayment wood to get the...

Page 11: ...ghten the mounting rail by tightening the flange nut of the cross connector to 26Nm drive SW13 See also figure 5 1 d as an example If more than one rail is to be connected insert the mounting rail con...

Page 12: ...wind convection runs underneath them This has an effect on the heat exchange capacity of the heat pump panels The minimum distance between the roof and the underside of the heat pump panels is 90mm T...

Page 13: ...plan of the Sunbeam Calculator for the ballast distribution 1 After assembling the Sunbeam mounting system the Triple Solar mounting rails 324200 must be fixed to the Sunbeam triangles by means of cr...

Page 14: ...d at the back side of the heat pump panels This TS clamping profile is required due to wind and tensile loads at the centre of the heat pump panel The aluminium frame that surrounds PV panels and prov...

Page 15: ...to a hole in the end profile on each side of the heat pump panel to prevent it from slipping See figure 7 2 a Figure 7 2 a panel with M8 bolt to prevent slipping 2 Lay down the outer heat pump panel a...

Page 16: ...igure 7 2 c connecting hoses mounted on one side 6 Place the next panel on the rails and secure with the M8 bolts against slipping Carefully push the entire panel sideways in one controlled movement t...

Page 17: ...d middle clamp Mounting the TS clamping profile Now that the whole row of panels is in place and it has been checked that the alignment of the panels is correct it is time to connect TS clamping profi...

Page 18: ...with a D Connecting the PV panels electrically The instruction for the electrical connection of the heat pump panels is identical to regular PV panels The electrical connection may only be carried ou...

Page 19: ...view for connecting optimizers It is important to avoid large induction loops in order to ground the PV cables correctly The correct way is to lay the electrical cables next to each other as much as...

Page 20: ...ource fluid Make sure that the flow in the source circuit is limited as little as possible e g by using knees and or pipes with an inner diameter that is too small Do not install any piping under the...

Page 21: ...n connection Attention Preferably connect the panel according to the Tichelman principle connect the cold pipe at the bottom of the panels the hot return pipe at the top Fittings Preferably use squeez...

Page 22: ...hose package 1 6x connection plug outside 2 3x valve inside outside 3 2x ribbed hose inside outside 900 1300mm 4 2x adapter x1 inside outside 5 4x T adapter 1 x x1 inside 6 2x ribbed hose 1 inside out...

Page 23: ...the panel field 6 kW to 8kW 26 mm 8 kW to 15kW 32 mm 15kW to 28kW 41 mm 28kW to 50kW 51 mm Hydraulic plan Fit a 3 bar pressure relief valve or use the supplied expansion vessel connection group 3 bar...

Page 24: ...er temperatures due to a higher viscosity Observe the supplier s instructions regarding concentration ratio toxicity and safety Check the mixing ratio of the glycol with a refractor device Make sure t...

Page 25: ...with the following insulation properties Vapour tight 19mm thick Minimum thermal conductivity 0 033 W mK For fixing the piping to the wall the following support is recommended to prevent cold bridges...

Page 26: ...101 mounting rail cover aluminium black anodising 2x 336101 Self drilling screw with EPDM ring 4 8x25mm stainless steel SW8 4x Instructions see corresponding images below 1 Slightly bend the mounting...

Page 27: ...remaining drinking water will affect the glycol ratio in the system The warranty provided by Triple Solar and Nibe expires with immediate effect Always first pressurize the installation with air to d...

Page 28: ...long and removed from the pipe system All loops are flushed sequentially After flushing the field is filled Careful venting System pressure at heat pump 2 4 bar System pressure on the roof Pressure on...

Page 29: ...conditions see www triplesolar eu Points of attention here Warranty conditions products Triple Solar gives a product warranty on the heat pump panels for a period of 10 years PV panels heat pumps and...

Reviews: