5
Installation
2B
Mount on Solid Brick
and Concrete Block
WARNING
• When installing wall mounts onto a concrete masonry unit (also known as a CMU or “cinder block”), verify that the actual
concrete thickness is at least 35 mm (1-3/8”) in order to hold the concrete anchors. DO NOT DRILL INTO MORTAR JOINTS!
Be sure to mount the assembled wall-mount plate with the included concrete anchors, D6 washers and anchor bolts
onto solid sections of the blocks. The solid sections can generally be found 25 mm (1”) toward the middle of the block
from either end. An electric drill on a slow setting is suggested to drill the hole rather than a hammer drill so as to avoid
breaking out the back of the hole when entering a hollow section.
• Installers must verify that the supporting surface will safely support the combined load of the equipment and all attached
hardware and components.
60 mm
(2.4 in.)
O10 mm
O(3/8 in.)
Find and mark
the exact
location of
mounting holes
Drill pilot holes
Screw the
assembled wall
plate onto the
wall
20 mm
Washer
Anchor
Bolt
Concrete
Anchor