COMMISSIONING
At this stage, temporarily fit the cover in order to
carry out the commissioning procedure.
The first operation of the shower is intended to
flush out any remaining unit debris and to make
sure the heater unit contains water before the
elements are switched on.
Refit the trimplate.
Turn the valve spindle fully clockwise until it hits
the 'stop'
(fig.14)
.
Turn the temperature control on the cover to the
minimum flow setting as shown in
(fig.15)
.
Offer the cover to the unit.
IMPORTANT:
DO NOT connect the 10-way
ribbon cable at this stage.
Carefully locate the cover into the backplate
and make sure that the wires are not trapped.
Guide the cover into position so that the control
spindle locates correctly (minor adjustment may
be necessary to align the control and spindle).
Should any difficulty arise, recheck the points
above.
While applying slight pressure to the front
cover, secure in position with the three retaining
screws.
Fit the flexible hose to the shower outlet making
sure the outlet of the hose is directed to waste.
Check the supplied sealing washer is in place.
DO NOT attach the showerhead at this stage.
Before turning on the electric and mains
water supplies to the shower, make sure the
temperature control is rotated fully clockwise to
the minimum flow position
(fig.15)
.
Note:
Failure to rotate fully clockwise may cause
the PRD to operate.
Turn on the water supply to the shower at the
isolating stopvalve. Switch on the electricity
supply to the shower at the isolating switch.
Wait until water starts to flow from the flexible
hose.
Slowly rotate the temperature control fully
anti-clockwise to the maximum flow position
(fig.16)
.
Commissioning
COMMISSIONING
INLE
T
>POM-GF30<
INLE
T
Fig.14
Temperature
control at
maximum
flow setting
Temperature
control at
minimum
flow setting
Fig.16
Fig.15
Summary of Contents for ASPIRANTE XR
Page 26: ...Aspirante xr 26 ...
Page 27: ...Aspirante xr 27 ...