17
INSTALLATION
OFF
ON
COMMISSION
OFF
ON
COMMISSION
8
check list
SECTION
TO DO BEFORE FITTING THE COVER
1.
Make sure the water supply is turned on to
the shower.
2.
Open the bleed screw on the pump unit
(fig.13)
by rotating two revolutions. When
water flows from the opening, this indicates
that any trapped air is vented and that the
pump unit is primed. The bleed valve
MUST
now be closed by rotating in the opposite
direction.
3.
Make sure the temporary locking screw on
the power selector is in place - see
fig.10
.
Fig.13
Fig.14
Commission
ON
= Pump
OFF
Bleed screw
Open
Commission
OFF
= Pump
ON
WARNING
Before fitting the cover the following
list
MUST
be checked to ensure the
commissioning procedure may be
carried out correctly.