6. Maintenance
Turn off and lock the main switch before you start with the
maintenance work of the lift!
The maintenance intervals indicated below apply to average
workshop use. The lift should be inspected more frequently for
severe use applications.
6.1. Maintenance schedule
Establish a periodic preventive maintenance procedure to ensure trouble free operation
and long service life.
Interval
Involved parts
maintenance tasks
1x per week
supporting frame
- check if the pads are in the correct position
pads
- lubricate slide rail and pads
all 6 month
greasing points
- check the slide rails and lubricate them if
necessary
nuts and bolts
- check all nuts and bolts for correct torque
tighten them if necessary
all 12 month
hydraulic system
- check fluid level
- clean oil tank and oil filter
- change the complete hydraulic oil
- check tightness of hoses and fittings
- check hoses and fittings for leakages