MASTERseries - Release 7.0
15
MASTERseries Quick Start Guide
2-Slot Chassis Installation
Alarm Lead Routing
To meet emissions standards, the alarm leads must be routed away from all other cables connected
to the chassis. These include the power, Ethernet, NMS, T1/E1, and V.35 cables. As an example,
you might route the alarm leads as shown below.
Applying Power
DANGER!
POSSIBLE SHOCK HAZARD EXISTS - PLEASE FOLLOW INSTRUCTIONS
CAREFULLY.
After all procedures in
Power Supply Installation and Cabling on page 9
and (optionally)
Alarm
Contacts on page 14
have been completed, apply power as follows:
1. If you have not yet done so, plug the power terminal block into the power entry panel.
2. Apply power to the chassis by turning on the power switch.
A green light should appear on the power LED on the front of the power supply.