Speed Gate Turnstile User Manual
4. Put the strong electric cable and weak electric cable through 3/4 "PVC pipe and
bury them in cement to the corresponding position.
5.
Open the case door, select one of the equipment as the reference (it is better to
choose the middle one as the reference), align the bolt hole of the machine seat
with the corresponding anchor bolt, and tighten the nut first.
6.
Refer to the wiring diagram, connect the power line and control line well, and
connect the system ground wire protection.
7.
After check, if the equipment status is normal, the following function debugging
can be carried out.
8.
Check the mains wiring according to the wiring diagram, check the power wiring
and other wiring of the whole equipment is correct, the debugging can be done
after confirmation.
6. Equipment function debugging
6.1 Key description
Long press "menu” for 3 seconds -- to enter the L-series, press "up” enter L-2...
Press "ok" again to enter the H-series, press up or down to make adjustment, press
"menu key" to return and save, and press "ok" to exit the setting option.
Long press "menu key" for 3 seconds -- enter l-1 and press "down key" plus value
d-2...
www.TURNSTILES.us | patrick.mcallister@TURNSTILES.us | 303-670-1099