background image

TFP1253

Page 7 of 8

DELTA 

CONTACTOR

ON/OFF 

SWITCH

FUSE

LINE CONTACTOR  

WITH INTEGRATED 

Y-D TIMER 

OVERLOAD 

RELAY

STAR 

CONTACTOR

TERMINAL 

BOARD

HOURMETER 

RUNNING HOURS

it controls, permission to shut down 

the affected fire protection systems 

must first be obtained from the proper 

authorities. All personnel who may 

be affected by this decision must be 

notified.
Inspection, testing, and maintenance 

must be performed in accordance 

with the requirements of the NFPA, and 

any impairment must be immediately 

corrected.
The owner is responsible for the inspec-

tion, testing, and maintenance of their 

fire protection system and devices in 

compliance with this document, as well 

as with the applicable standards of any 

authorities having jurisdiction. Contact 

the installing contractor or product 

manufacturer with any questions.
Automatic sprinkler systems are rec-

ommended to be inspected, tested, 

and maintained by a qualified Inspec-

tion Service in accordance with local 

requirements and/or national codes.

Maintenance of the Nitrogen 

Generator

The nitrogen generator cabinet con-

tains three separate cartridge filters. 

It is recommended that each of the 

filter cartridges be replaced as part of 

an annual preventative maintenance 

program. In some environments it may 

be necessary to replace filters more 

frequently. When maintained properly 

the nitrogen separation membrane will 

provide up to 20 years of service life.

Filter Replacement Procedure

With reference to Figure 4, perform 

the following steps when replacing the 

cartridge filters located in the Filter 

Housing.

Step 1.

 Turn the power supply to the 

unit off.

Step 2.

 Close the Inlet and Outlet Ball 

Valves, and open the Bypass Ball Valve.

Step 3.

 Depressurize the nitrogen gen-

erator internal inlet piping by slowly 

opening the Depressurization Ball 

Valve in the cabinet to the left of the 

filter housing.

Step 4.

 Remove the filter housing by 

pulling down on the blue housing lock 

and turning the filter housing count-

er-clock wise.

Step 5.

 Once the filter housing has 

been removed, the filter cartridge 

inside is removed by first unscrewing 

the black retaining disc at the base of 

the cartridge and then pulling down on 

the cartridge. Discard the old filter car-

tridge and replace it with the appropri-

ately marked filter cartridge from the 

filter replacement kit by pushing up 

so that it fits snugly onto the receiving 

cylinder in the upper part of the filter 

housing. Hand tighten the black retain-

ing disc back onto the central metal 

threaded rod.

Step 6.

 Replace the filter housing by 

pushing up into position and turning the 

housing clockwise until blue housing 

lock locks into place.

Step 7.

 Repeat Step 4 through Step 6 

for each additional filter.

Note:

 Filters 2 & 3 do not have a black retain-

ing disc, filters screw directly into housing.

FIGURE 3C 

MODEL TNGC-1150/1500/2000/3000 AIR COMPRESSOR 

EMEA AND APAC POWER SUPPLY CONNECTIONS

Summary of Contents for NG-1 1150

Page 1: ...to TFP1262 for more information on TYCO Dry Air Vent TAV D and to TFP1263 for more information on TYCO SMART Air Vent TSV D System Assembly The TYCO Nitrogen Generator unit includes the following comp...

Page 2: ...605 1150 4353 2300 8706 NG 1 1500 24 3 688 11000 41640 1440 5451 2880 10902 NG 1 2000 24 688 18500 70030 2025 7666 4050 15331 NG 1 3000 35 992 22500 85172 2900 10978 5800 21955 Notes a Capacity based...

Page 3: ...l Cabinet Dimensions See Table A Weight See Table A Operating Performance See Table B Temperature Range 40 F 5 C to 105 F 40 C Power Supply 120 VAC Single 1 phase 60Hz dedicated circuit 230 VAC Single...

Page 4: ...panel for wall mount ing using standard anchors Step 2 Power Supply The Nitrogen Generator requires a ded icated power supply that connects to the terminal blocks in the nitrogen gen erator cabinet Se...

Page 5: ...ENERATOR RUNNING OUTPUT BYPASS MODE ALARM OUTPUT LEAK MONITORING OUTPUT POWER ON OFF OUTPUT NITROGEN SUPPLY LINE PRESSURE OUTPUT L1 N G PRESSURE SWITCH INCOMING POWER FUSE BOX BUILDING MANAGEMENT SYST...

Page 6: ...compressors in EMEA and APAC the air discharge plumb ing should first be connected to the WSD 25 water separator which then is to be connected to the inlet of the nitro gen generator Step 4 Plumb the...

Page 7: ...gen separation membrane will provide up to 20 years of service life Filter Replacement Procedure With reference to Figure 4 perform the following steps when replacing the cartridge filters located in...

Page 8: ...10 Close the depressurization ball valve The Nitrogen Generator can now be placed back into service Step 11 Turn the power supply to the unit ON Step 12 Close the Bypass Ball Valve Step 13 Open the In...

Reviews: