Qwik Install
STEP 1:
Select install location where southern sky has no obstructions
that could cause shading on solar panels.
STEP 2:
Pour a foundation big enough to hold solar mount anchors
and also provide level support for battery box. See detailed instructions
in solar mount instructions.
STEP 3:
Assemble solar array with mount using solar mount instruc-
tions.
Warning:
Batteries are very heavy, always use 2 people when
handling the batteries.
STEP 4:
Place battery box under solar panels. Install 4 batteries in the
box. Use handles to lower batteries into the box.
Remove the battery
fuse from the battery cable before proceeding
. Connect all 4 batter-
ies in series configuration (Positive to Negative to Positive...).
STEP 5:
Install DIN rail to enclosure using the two screws provided.
Install MPPT solar controller to DIN Rail. Remove the Large Green
Connector from the unit.
STEP 6:
Find the temperature sensor cable that came with the MPPT
Solar Controller and connect the side with the ring lug to one of the bat-
teries positive or negative terminals, it doesn
’
t matter which one. Con-