Qwik Install
STEP 1:
The UPSPro
®
i s Solar Ready™ so a solar panel can be add-
ed at any time to provide supplemental or full time power.
STEP 2:
Install controller to inside cover of housing using Velcro tape.
Be sure that controller doesn’t interfere with batteries when cover is
closed. Mount all the way to lower right corner to give room for CAT5
cables.
STEP 3:
Mount any electronics boards to the metal plate. Install a
CAT5 cable between the controller POE OUT and the electronics.
There is a secondary voltage output on the back of the controller which
can be used in addition to the POE OUT. The secondary output is equal
to the battery voltage.
STEP 4:
Install the enclosure to a pole using stainless steel hose
clamps or to a wall using lag bolts.
STEP 5:
Install batteries into enclosure with Velcro straps.
STEP 6:
Connect the Battery cables to Controller BAT terminals. Be
sure to observe polarity. Black wire connects to battery negative termi-
nal and BAT(-) terminal on the controller. When a fully charged battery
is connected, the Green LOA LED should light on controller. Power
should also be present at the POE output and the green secondary
power output.
STEP 7:
Install CAT5 cable between POE inserter/Power Supply inside
building and the UPSPro
®
unit controller RJ45 IN connector. It is highly