10
NOTICE
The gasketed vent system components pictured below in Figure A are being phased in and each vent component
is interchangeable with the previously supplied gasket-less venting components. The newer vent components
are generally quicker and easier to join, as they do not require the sealant application and their clamp bands
are attached.
In the event a gasketed vent component and a gasket-
less vent component must be interconnected, follow the
instructions associated with Figure 8B or 8C. The two
guiding principles of these instructions are as follows:
1) Any joining of vent components that involves
at least one gasket-less vent component
always requires the sealant application.
2) The female end of a gasket-less vent
component always requires a clamp band,
regardless of the design of the mating male
vent component.
Each gasket-less vent component is supplied with a clamp band and sealant.
A Vent Transition Kit, part number 6116302, is available that contains one clamp band and one 3 ounce tube
of sealant.
Table 7: Maximum Equivalent Vent Length
V. Venting
Figure A: U.S. Boiler Company Vent
A.
General Guidelines
1. Vent system installation must be in accordance with
National Fuel Gas Code
, NFPA 54/ANSI Z221.3,
Venting of Equipment, or applicable provisions of
local building codes. Contact local building or fire
officials about restrictions and installation inspection
in your area.
2. This boiler requires a Special Gas Vent. The product
is designed to use supplied AL 29-4C
®
Stainless
Steel vent system components. The following
manufacturer's offer similar AL 29-4C
®
components
and are approved for use with this product: Heat-
Fab - Saf-T-Vent (800-772-0739); Flex-L
International - Star-34 (800-561-1980); Protech
Systems, Inc. - FasNSeal™ (800-766-3473); and Z-
Flex U. S., Inc. - Z-Vent (800-654-5600). The use
of these alternate manufacturer's venting systems
will require adapters to connect to the supplied vent
connector and vent terminal. These adapters are not
supplied with this boiler and should be obtained
from the supplier of the alternate manufacturer's
venting system. See Table 8 for complete parts list.
WARNING
Do not use this boiler with galvanized, 304 or 316
stainless steel or any other non AL29-4C
®
based
vent systems.
3. Vent length restrictions are based on equivalent
length of vent pipe (total length of straight pipe plus
equivalent length of fittings). Maximum vent length
is listed in Table 7. Do not exceed maximum
lengths. Minimum vent length is 8 feet. Table 8 lists
equivalent length for fittings. Do not include Vent
Terminal in equivalent feet calculation.
4. Do not install venting system components on the
exterior of the building except as specifically
required by these instructions.
B.
Removal of Existing Boiler.
For installations not
involving the replacement of an existing boiler, proceed
to Step C.
When an existing boiler is removed from a common
venting system, the common venting system is likely
to be too large for proper venting of the remaining
appliances. At the time of removal of an existing
boiler, the following steps shall be followed with each
appliance remaining connected to the common venting
system placed in operation, while the other appliances
remaining connected to the common venting system
are not in operation:
1. Seal any unused openings in the common venting
system.
IN3PV
IN4PV
IN5PV
IN6PV
45
35
35
35
Summary of Contents for INDEPENDENCE IN3PV
Page 7: ...7 Figure 4 Steam Piping IN3PV Figure 3 Trim Installation III Steam Piping and Trim continued...
Page 29: ...29 SERVICE RECORD DATE SERVICE PERFORMED...
Page 42: ...42 SERVICE RECORD DATE SERVICE PERFORMED...
Page 43: ...43 SERVICE RECORD DATE SERVICE PERFORMED...
Page 44: ...44 U S Boiler Company Inc P O Box 3020 Lancaster PA 17604 1 888 432 8887 www usboiler net...