background image

5

rating of 1 perm or less with openings gasketed 

and sealed, and;

b.  Weather-stripping has been added on openable 

windows and doors, and;

c.  Caulking or sealants applied in joints around 

window and door frames, between sole plates 

and floors, between wall-ceiling joints, between 

wall panels, at plumbing and electrical 

penetrations, and at other openings.

5.  For boiler located in an 

unconfined space in a 

building of

 

other than unusually tight construction

adequate combustion and ventilation air is normally 

provided by fresh air infiltration through cracks 

around windows and doors.

6.  For boiler located within 

unconfined space in 

building of unusually tight construction

 or within 

confined space

, provide outdoor air through two 

permanent openings which communicate directly or 

by duct with the outdoors or spaces (crawl or attic) 

freely communicating with the outdoors. Locate one 

opening within 12 inches of top of space. Locate 

remaining opening within 12 inches of bottom of 

space. Minimum dimension of air opening is 3 

inches. Size each opening per following:
a.  Direct communication with outdoors. Minimum 

free area of 1 square inch per 4,000 Btu per hour 

input of all equipment in space.

b.  Vertical ducts. Minimum free area of 1 square 

inch per 4,000 Btu per hour input of all 

equipment in space. Duct cross-sectional area 

shall be same as opening free area.

c.  Horizontal ducts. Minimum free area of 1 square 

inch per 2,000 Btu per hour input of all 

equipment in space. Duct cross-sectional area 

shall be same as opening free area.

  Alternate method for boiler located within confined 

space. Use indoor air if two permanent openings 

communicate directly with additional space(s) of 

sufficient volume such that combined volume of all 

spaces meet criteria for unconfined space. Size each 

opening for minimum free area of 1 square inch per 

1,000 Btu per hour input of all equipment in spaces, 

but not less than 100 square inches.

7.  Ventilation Duct Louvers and Grilles. Equip outside 

openings with louvers to prevent entrance of rain 

and snow, and screens to prevent entrance of insects 

and rodents. Louvers and grilles must be fixed in 

open position or interlocked with equipment to open 

automatically before burner operation. Screens must 

not be smaller than ¼ inch mesh.

  Consider the blocking effect of louvers, grilles and 

screens when calculating the opening size to provide 

the required free area. If free area of louver or grille 

is not known, assume wood louvers have 20-25 

percent free area and metal louvers and grilles have 

60-75 percent free area.

G

.

  Do not install boiler where gasoline or other flammable 

vapors or liquids, or sources of hydrocarbons (i.e.  

bleaches, cleaners, chemicals, sprays, paint removers, 

fabric softeners, etc.) are used or stored.

CAUTION

Avoid operating this boiler in an environment 

where saw dust, loose insulation fibers, dry wall 

dust, etc. are present.  If boiler is operated under 

these conditions, the burner interior and ports 

must be cleaned and inspected daily to insure 

proper operation.

II. Unpack Boiler

CAUTION

Do not drop boiler.  Do not bump boiler jacket 

against floor.

A.

  Move boiler to approximate installed position.

B.

  Remove all crate fasteners.

C.

  Lift outside container and remove with all other 

inside protective spacers and bracing.  Save two of the 

wooden slats from the container sleeve for use in Steps 

E and F.

D.

  Remove all boiler hold-down fasteners.

E.

  Tilt the boiler to one side and slide a wooden slat under 

the two raised feet.

F.

  Tilt the boiler to the other side and slide another 

wooden slat under the two raised feet.

G.

  Slide the boiler forward or backward off the skid using 

the two wooden slats as runners.

H.

  Move boiler to its permanent location.

I. Pre-Installation (continued)

Summary of Contents for INDEPENDENCE IN3PV

Page 1: ...E P E D N I V P R E L I O B D E R I F S A G For service or repairs to boiler call hour heating contractor When seeking information on boiler provide Boiler Model Number and Serial Number as shown on...

Page 2: ...tuation which if not avoided could result in death serious injury or substantial property damage CAUTION Indicates a potentially hazardous situation which if not avoided may result in moderate or mino...

Page 3: ...stem is necessary to allow noxious fumes that could cause injury or loss of life to vent safely and will contribute toward maintaining the boiler s efficiency This boiler is supplied with safety devic...

Page 4: ...and combustible material in accordance with local fire ordinance Refer to Table 1 for minimum listed clearance from combustible material Recommended service clearance is 24 inches from left side righ...

Page 5: ...onfined space Size each opening for minimum free area of 1 square inch per 1 000 Btu per hour input of all equipment in spaces but not less than 100 square inches 7 Ventilation Duct Louvers and Grille...

Page 6: ...stall zone circulator and strainer in supply piping Install check valve to prevent gravity circulation of boiler water 2 Limit Install temperature limit control Honeywell L4006A or equal in Tapping P...

Page 7: ...7 Figure 4 Steam Piping IN3PV Figure 3 Trim Installation III Steam Piping and Trim continued...

Page 8: ...ing natural gas Table 5 lists equivalent pipe length for standard fittings 4 Specific gravity of gas Corrections for the specific gravity of natural gas can be found in Table 6 For materials or condit...

Page 9: ...e For all testing over psig boiler and its individual shutoff valve must be disconnected from gas supply piping For testing at psig or less isolate boiler from gas supply piping by closing boiler s in...

Page 10: ...omponents and are approved for use with this product Heat Fab Saf T Vent 800 772 0739 Flex L International Star 34 800 561 1980 Protech Systems Inc FasNSeal 800 766 3473 and Z Flex U S Inc Z Vent 800...

Page 11: ...use 7 Any improper operation of the common venting system should be corrected so the installation conforms with the National Fuel Gas Code NFPA 54 ANSI Z223 1 When resizing any portion of the common v...

Page 12: ...d end only female bell end accepts next fitting or pipe NOTICE Cut must be square with pipe and filed or sanded smooth before joining Carefully ensure roundness of cut pipe by hand with gloves before...

Page 13: ...pipes in horizontal runs at top to avoid condensate from lying on the seams Figure 9 Horizontal Vent Installation V Venting continued CAUTION Moisture and ice may form on surfaces around vent terminal...

Page 14: ...ces above the boiler with materials having a fire resistance rating at least equal to the rating of adjoining floor or ceiling Maintain minimum clearance to combustible materials Note For one or two f...

Page 15: ...8 12 to 20 12 7 ft 6 in Over 20 12 to 18 12 8 ft d Install storm collar on vent pipe immediately above flashing Apply sealant between vent pipe and storm collar e Attach Vent Terminal 7 Install conden...

Page 16: ...ower to thermostat Connect circuit to brown wire to control boiler operation Set thermostat heat anticipator to 0 4 amps See Figure 15 D Alliance SL Indirect Water Heater if used See Figure 15 Ladder...

Page 17: ...ect manometer to gas manifold Use 1 8 NPT tapping provided 4 Temporarily turn off all other gas fired appliances D Follow Operating Instructions to place boiler in operation See Figure 21 E Sequence o...

Page 18: ...ts within 10 seconds control returns to normal sequence If flame out of sequence remains longer than 10 seconds control will resume normal opera tion 1 hour after error is corrected Check for pilot fl...

Page 19: ...er sensor cracked ceramic insulator replace if needed Figure 17B Measuring Pilot Flame Current with Micro ammeter v Check the pilot flame It must be blue steady and envelop the flame sensing rod 3 8 t...

Page 20: ...SARY TO RECYCLE THE CALL FOR HEAT MORE THAN ONCE TO CLEAR THE PILOT SUPPLY TUBES OF AIR NOTE IF CONTROL GOES INTO LOCKOUT OR RETRY DELAY RESET THE CALL FOR HEAT CHECK CONTINUITY OF IGNITION CABLE AND...

Page 21: ...below observed pressure Main burners and pilot burner should extinguish and blower stop 3 Adjust limit to setting above observed pressure Ignition sequence should begin 4 Adjust thermostat to lowest...

Page 22: ...y No 4D iii Reinstall gas orifices and main burners Measure input rate 6 Recheck Main Burner Flame 7 Return other gas fired appliances to previous conditions of use M Clean Heating System Oil from new...

Page 23: ...triction 2 Fill boiler to top of gauge glass 3 Remove safety valve 4 Pour recommended boil out compound into boiler through safety valve opening 5 Reinstall safety valve in Tapping E with spindle in v...

Page 24: ...ructions to place boiler in operation See Figure 21 Allow boiler to steam for 10 minutes Drain one quart of water from lower Gauge Glass fitting 25 Drain second quart sample from lower Gauge Glass fit...

Page 25: ...reens securely in place 2 Vent terminal and wall thimble if used must be weather tight 3 Vent pipe must be full round shape and show no damage from impact or excessive temperature 4 Vent pipe must be...

Page 26: ...original location See Table 14 b Main burners must be properly secured in burner tray slot at rear of firebox and over gas orifice See Figure 23 c Pilot gas supply igniter sensor cable and ground wire...

Page 27: ...Figure 25 L404F Pressuretrol Boiler Model Minimum Vacuum IN3PV 0 40 inches w c IN4PV 0 40 inches w c IN5PV 0 70 inches w c IN6PV 0 70 inches w c VIII Service Instructions continued 4 Stop boiler remo...

Page 28: ...Long sleeved loose fitting clothing 3 Gloves 4 Eye Protection Take steps to assure adequate ventilation Wash all exposed body areas gently with soap and water after contact Wash work clothes separatel...

Page 29: ...29 SERVICE RECORD DATE SERVICE PERFORMED...

Page 30: ...ECONDS BEFORE SPARK BEGAN NO REPLACE IGNITION MODULE YES TURN ON GAS SUPPLY DOES PILOT BURNER LIGHT YES 24 VOLTS ACROSS GAS VALVE TERMINALS PV AND MV PV YES NO NO YES NO OPEN VALVES ALL MANUAL GAS VAL...

Page 31: ...NC NO 24 VOLTS AT BOTH L W C O TERMINALS B B YES NO REFER TO L W C O MANUFACTURER S TROUBLESHOOTING INSTRUCTIONS NO FILL BOILER TO NORMAL WATERLINE NO GAUGE PRESSURE LESS THAN LIMIT CUT IN SETTING ALL...

Page 32: ...2J Blower 1 6111714 1 6111715 2K Orifice Plate Gasket 2 Included in Key No 2J 2 8206042 2 8206035 2L Orifice Plate 1 61110036 1 61110046 1 61110056 1 61110066 2M Washer 1 4 4 80860603 2N Hex Locknut...

Page 33: ...sembly 4 6186001 3E1 Base Leg Included in Key No 3E 4 71860021 3E2 Nylon Glide Included in Key No 3E 1 per leg 8186006 3F Burner Access Panel 1 618600361 1 618600461 1 618600561 1 618600661 3G Left En...

Page 34: ...8236099 8 8236099 4B Main burner with 60 Pilot Bracket 1 8236098 4C Manifold 1 82260033 1 82260043 1 82260053 1 82260063 4D Main Burner Orifice 45 Pink 3 822711 5 822711 7 822711 9 822711 4E Screw Mac...

Page 35: ...B1206 1 103704 01 5B Pilot Orifice Natural Gas Honeywell 388146NE Included with Key No 5A 5C Compression Nut Fitting 1 8 OD x 1 4 NPT Included with Key No 5A and 5E 5D Pilot Tubing 1 8 OD x 40 1 82361...

Page 36: ...4100440 1 604100540 1 604100640 6E Blower Access Panel 1 604100371 1 604100471 1 604100571 1 604100671 6F Rear Panel 1 604100350 1 604100450 1 604100550 1 604100650 6G Front Top Panel 1 604100360 1 60...

Page 37: ...Steam Gauge 0 30 psi 2 1 2 Dia 1 100325 01 9B Drain Valve Conbraco 31 612 02 1 806603012 9C Bushing Hex 2 NPT x 3 4 NPT 1 806600515 9D Gauge Glass Set 9 Glass Conbraco 21 104 10 1 8056128 9E Limit Ho...

Page 38: ...Bracket 1 7186018 10D1 Screw Sheet Metal 8 x 1 2 1 80860019 10E Suction Pressure Switch Red 1 60160876 Suction Pressure Switch Lt Blue 1 60160877 10F Silicone Tubing 1 8 O D x 20 1 7016020 10G Transf...

Page 39: ...ription Quantity Part Number IN3PV IN4PV IN5PV IN6PV 11 Gasketed Vent Accessory Carton Includes 11A 11B 61110128 61110129 11A Vent Connector 1 8116306 1 8116307 11B Vent Terminal 1 8116310 IX Repair P...

Page 40: ...nd Gasketed Male Vent Joint Detail Figure 9 13 Horizontal Vent Installation Figure 10 14 Horizontal Vent Terminal Figure 11 14 Vertical Vent Installation Figure 12 15 Vertical Vent Tee Installation Fi...

Page 41: ...Lengths Table 6 9 Specific Gravity Correction Factors for Natural Gas Section V Venting Table 7 10 Maximum Equivalent Vent Length Table 8 11 Vent System Components Table 9 15 Minimum Vent Height Abov...

Page 42: ...42 SERVICE RECORD DATE SERVICE PERFORMED...

Page 43: ...43 SERVICE RECORD DATE SERVICE PERFORMED...

Page 44: ...44 U S Boiler Company Inc P O Box 3020 Lancaster PA 17604 1 888 432 8887 www usboiler net...

Reviews: