15
Figure 20: Securing Draft Hood to Canopy
A.
Remove crate
and move boiler to permanent position
as detailed in Section III: Semi-Pak Boiler Assembly.
B.
Remove Jacket Front Panel.
See Figure 35.
C.
Remove poly bag
from vestibule area.
D.
On Steam Boilers with probe low water cutoff
the
L404 pressure limit/control has been packed in the
vestibule area.
1. Screw the pressure limit/control onto the syphon.
DO NOT TWIST CONTROL. Use wrench on hex
fitting at bottom of control. See Figure 16.
2. Snap the electrical conduit from the adjacent
junction box into the hole in the control.
3. Open the control's clear cover and attach the two (2)
wires in the conduit to the two (2) unused screw
terminals.
IV. Packaged Boiler Assembly
Figure 19: Draft Hood Attachment
E.
Install Jacket Front Panel.
F.
Install Draft Hood
. Models IN3I through IN9I.
1. Locate and open "Rear Draft Hood Carton".
2. Position Draft Hood on Canopy Rear Flange. See
F
igure 19. Top canopy flange must fully engage
"U"-shaped draft hood flange for proper installation
and operation. Care must be taken to assure that
draft hood is level.
3. Secure Rear Draft Hood to Canopy with wing nuts
provided. See Figure 20.
WARNING
Installation of this boiler should be undertaken
only by trained and skilled personnel from a
qualified service agency.
WARNING
Do not alter boiler draft hood or place any
obstruction or non-approved damper in the
breeching or vent system. Flue gas spillage can
occur. ETL/ETLC certification will become void.
Summary of Contents for INDEPENDENCE
Page 4: ...4 Figure 1 Dimensional Drawing...
Page 56: ...56 Manifold and 1 Main Burners XI Repair Parts continued...
Page 62: ...62 XI Repair Parts continued...
Page 64: ...64 XI Repair Parts continued...
Page 72: ...72 U S Boiler Company Inc P O Box 3020 Lancaster PA 17604 1 888 432 8887 www usboiler net...