III: INSTALLATION INSTRUCTIONS
A.
REMOVE CRATE
-
1. Remove all fasteners at crate skid.
2. Lift outside container and remove with all other
inside protective spacers and bracing. Remove
Parts Carton containing Safety Relief Valve, Boiler
Drain Valve, Circulator, Fittings and Miscellaneous
Hardware.
B.
REMOVAL OF BOILER FROM SKID
1. Boiler is secured to base with 4 bolts, 2 on left side
and 2 on right side, see Figure 2. Remove all bolts.
Figure 2: Removal of Boiler From Skid
2. Tilt boiler to right and to rear. Using right rear leg
as pivot, rotate boiler 90° in a clockwise direction,
and lower left side of boiler to floor. Tilt boiler
and remove crate skid. Care should be exercised to
prevent damage to Jacket or Burner.
C.
MOVE BOILER TO PERMANENT POSITION
by sliding or walking.
D.
INSPECT COMBUSTION TARGET WALL
.
1. OPEN FLAME OBSERVATION DOOR on front of
boiler.
2. Use flashlight to inspect Target Wall secured to rear
section with silastic. If damaged, replace.
WARNING
Any combustion chamber insulation which was
damaged must be replaced immediately.
E.
INSTALL CANOPY
The canopy is shipped in a separate carton.
1. Open canopy carton and remove canopy.
2. Remove two (2) sheet metal screws securing front of
jacket top panel and(2) sheet metal screws near the
top of both side panels. Pull side panels outward to
allow jacket top panel to swing upward as shown in
Figure 3, Step 1.
Figure 3:
Installation of Canopy (See text for proper procedure)