Take care to use proper lifting equipment and
procedures. Drift pins may be useful for locating
hopper mating sections. With the hopper section still
supported, use hardware to bolt the sections
together. Once all hardware is in place, go back and
fully tighten all hardware on mating pads and all
bracing. Disconnect the crane.
CONE ASSEMBLY
Series C190
- inlet can be rotated at 45°
increments from the base.
Series C200 and C240
- inlets can be rotated at 45°
increments.
Series C3000 and C3600 - inlets can be rotated at
221/2° increments.
Series C4400
- inlet can be rotated at 15°
increments.
The outlet (fan housing) on all models can be rotated
at 45° increments. Once correct positioning is
obtained, lay two ribbons of sealant around the bolt
circle of the fan housing and/or flange rings to
ensure airtight seal. Re-bolt the fan housing.
If discharge direction must be changed on the C3600
or C4400 series cyclones after unit has been
delivered (or if collector must be moved), the upper
cylinder/blower assembly must be re-oriented on the
ground because of the considerable force that may
be required to rotate the housing.
Place the upper cylinder/blower assembly on the
ground and firmly secure. To change the position of
the housing discharge in relation to the inlet, proceed
as follows:
1. Remove weather/belt guards.
2. Secure the blower package with a sling from a
crane or forklift attached to the channel on the
blower package.
3. Loosen and remove the bolts on the blower
package cover plate.
4. Lift fan/motor assembly out of fan housing and
support properly on ground.
5. Loosen and remove the bolts holding the blower
housing to the upper cylinder.
6. Rotate blower housing to the desired position.
Housing may stick because of sealant. Scrape the
old sealant off the barrel top and fan housing, then
reseal using silicone sealant. Apply a ribbon of
sealant on both sides of bolt pattern.
7. Reassemble parts in reverse order.
The blower package can now be re-installed. Apply a
ribbon of sealant to each side of bolt circle on top of
the blower housing. Gently lower the blower package
in place, making sure the terminal box on the motor
is facing desired direction. Use hardware provided
and secure package.
Install the cone assembly by setting the cone on top
of the base. No sealant is required at this joint for
the 1D and 2D units. Sealant is required for hopper
base units. The cones are symmetrical so there is no
specific orientation to consider. Using hardware
provided, fully secure cone to base (see Figure 4).
INLET AND OUTLET TRANSITION
INSTALLATION
Each Cyclone Dust Collector has its own bolt-on inlet
and outlet transitions. The model C192 transitions
are welded on the assembly. When mounting the
inlet transition, always make sure the top of the
transition is up. (see Figure 6). If the transition is
mounted improperly, unit efficiency will be
adversely affected.
Do not attempt to change the size of the inlet. If the
cyclone is operated with more than the maximum
permissible inlet area, the motor may become
overloaded.
INLET AND OUTLET DIRECTION CHANGE
Check to be sure the inlet and the fan discharge are
facing the desired direction. If not, they can be
rotated. The inlets on the various models can be
rotated as follows:
!
WARNING
In preparing to assemble the cyclone to its stand
or hopper, connect a lifting sling to at least four
positions on the cyclone. Distribute the load
evenly. Location must be clear of all obstructions
such as utility lines or roof overhangs.
CAUTION
Do not rest fan on the ground, as the fan may
become damaged.
Revised 06/07
C-Series
Cyclone Dust Collector
9
Summary of Contents for C Series
Page 1: ...High Efficiency C Series Cyclone Dust Collector OWNER S MANUAL ...
Page 7: ...Figure 2 Typical Installation Diagram CYCFIG2 Revised 06 07 C Series Cyclone Dust Collector 4 ...
Page 19: ...Figure 13 Wiring Diagram 04 1534 Revised 06 07 C Series Cyclone Dust Collector 16 ...
Page 31: ...28 Revised 06 07 C Series Cyclone Dust Collector This page intentionally left blank ...