background image

Instructions for use (rev 011221) 

e.ON sinter fast + 

 

UGIN DENTAIRE 

 

4

 

 

-

 

For moving:

 

-

 

take hold the furnace by its base: 

NEVER LIFT BY UPPER PART OF FURNACE.

 

-

 

the furnace must remain in an upright position: 

NOT HORIZONTAL POSITION.

 

-

 

do not leave any accessories or the support in the heating chamber. 

-

 

Never use the furnace without support.

 

-

 

Use only the 

support,

 

tray for sinterizing and cover

 provided by UGIN DENTAIRE. Before use, 

check it (no dirt or damage). 

If damaged: do not use.

 

-

 

Respect the positioning of support (base and  additional raise support) and the maximum 
number of trays to stack

 

(see chapter 6.7)

: damage equipment risk. 

 

-

 

The chamber is made up refractory ceramic fibers. 

-

 

Handle carefully. 

-

 

They can release dust: remove with a vacuum cleaner - do not blow or use compressed 
air. 

 

-

 

Use only 

genuine spare parts

. The use of non-original spare parts voids any warranty for your 

device. 

-

 

Do not introduce  stranger objects  inside

  the  unit during  the  maintenance operations.  It is 

forbidden to modify the material without authorization. 

-

 

Do not execute different operations of maintenance

 from those listed in this manual.  Any 

operation not included in this manual can involve risks. 

-

 

For  any  further  information  concerning  installation,  maintenance  and  use,  contact  the 

customer’s service UGIN DENTAIRE.

 

 

Summary of Contents for e.ON sinter fast

Page 1: ...INSTRUCTIONS FOR USE Sintering furnace R v 011221...

Page 2: ...CTIONS 13 6 4 2 1 EXAMPLES OF CALCULATION 14 6 5 PARAMETER SETTING 14 6 6 PROGRAMS 15 6 6 1 PROGRAM PRE RECORDERED No 1 conventional cycle 15 6 6 2 PROGRAM PRE RECORDERED No 2 short cycle for up to 5...

Page 3: ...fast UGIN DENTAIRE 2 A EQUIPEMENT DESCRIPTION 3 6 7 N DESCRIPTION 1 Upper part of furnace 2 Platform 3 Support base and additional raise support 4 Touch screen 5 Power switch ON OFF rear side 6 Tray f...

Page 4: ...e furnace head surface platform support tray for sinterizing and cover may reach high temperatures do not touch Wear suitable gloves for handling prosthetic objects tray for sinterizing and cover and...

Page 5: ...the maximum number of trays to stack see chapter 6 7 damage equipment risk The chamber is made up refractory ceramic fibers Handle carefully They can release dust remove with a vacuum cleaner do not...

Page 6: ...must be disposed in accordance with applicable regulations in force 2 EC DECLARATION OF CONFORMITY The equipment s EC declaration of conformity is provided as appendix of instructions for use Content...

Page 7: ...Maximum temperature 1 730 C Operating temperature Less than 1 650 C Temperature accuracy 1 C Heating rate To 94 C minute maximum Screen High definition colour touch screen 7 155x87mm Number of progra...

Page 8: ...ts base never lift by upper part of furnace For transport the furnace must remain in an upright position not horizontal position Install the furnace in the packaging with the protective elements Also...

Page 9: ...rs and or other equipment that release heat Despite excellent insulation the furnace provides heat and in the long term can discolour surfaces that are nearest Do not shake the furnace avoid vibration...

Page 10: ...crew Remove carefully the cushioning foam pad protecting heating elements Then visually inspect the heating element no damage Avoid handling Install exhaust pipe a Install the conduit on the intended...

Page 11: ...y inspect the heating elements First time use press the arrow key upward and arrow key downward on touch screen Check the alignment of the platform with the base of the chamber movements must be made...

Page 12: ...ls Then press descent platform key ARROW KEY DOWNWARD an alert message appears in the status bar bottom of the screen Menu MENU or logo Microsoft Pull down menu appears as shown below Working interfac...

Page 13: ...is displayed on the screen For each program number the cycle parameters are displayed as a chart C represents temperature C and T represents time minutes Each program is two pages the first page disp...

Page 14: ...4 Final temperature of third stage and start temperature of fourth stage If necessary the parameters are programmed as for the previous steps Last time 121 Indicates the end of program temperature con...

Page 15: ...ature remains to 1490 C Time remains 10 minutes Time 03 10 minutes T03 10 minutes Zirconia SINTERING TEMPERATURES are given as indicative by disc manufacturer If necessary this one can be adjusted fro...

Page 16: ...1000 C Check with the cycle diagram that the furnace follows the requested temperature curve 6 6 1 PROGRAM PRE RECORDERED No 1 conventional cycle C01 50 0 C06 900 0 C11 0 0 C16 0 0 T01 50 T06 121 T11...

Page 17: ...T BE CARRIED OUT AS A PRECAUTIONARY MEASURE BEFORE THE FIRST USE OF THE FURNACE start the pre recorded program number 40 If use different types of zirconia zirconia of different brands or zirconia wit...

Page 18: ...dditional raise support on the platform during carry out a decontamination cycle ADVICE add in a tray with or without a cover white Zirconia smashed in multiple small pieces absorption of pollutants o...

Page 19: ...Clean with a vacuum cleaner if necessary see chapter 8 If the support is damaged or cracked do not use and replace it It is composed of a base and additional raise support Always position the two part...

Page 20: ...o trays Place the tray s at the center of support on the base and additional raise support Note if the zirconia beads are discoloration in yellow colour they must be replaced 6 7 2 2 TO PERFORM A SHOR...

Page 21: ...RUN the furnace starts to rise in temperature b the platform rises and stays closed 5 to 10 seconds c the platform goes down partially and holds about 5 min d the platform rises without closing comple...

Page 22: ...osition When the furnace is in standby or off the platform must be in the high position to avoid condensation Do not touch the display during a cycle to avoid manual interruption of the programme At t...

Page 23: ...without a cover white Zirconia smashed in multiple small pieces or powder Nacera Clean absorption of pollutants After running the program check the condition of the rods still whitish traces still con...

Page 24: ...s cleaner Cleaning wipes for optic products can also be used For avoid screen damage do not use a sharp object to operate the touchscreen Remove any pearl of small pieces stuck between the display and...

Page 25: ...of heating elements with a wrench supplied as an accessory Repeat for all the heating elements to replace 3 Unscrew the support elements of heating element with a wrench supplied as an accessory 4 Re...

Page 26: ...perature and time Adjust sintering temperatures if necessary see chapter 6 4 The furnace does not heat up It is necessary to test the continuity of the rods Do not use the furnace risk of material dam...

Page 27: ......

Reviews: