Safety

Tips and recommendations

It is necessary to observe the safety notes written in 
these operating instructions in order to reduce the risk of 
personal injuries and damages to property. 

2.2 Obligations of the operating company

Operator

The operating company is the person who operates the 
crane scales for business or commercial reasons by her-
self, or leaves it to a third party for use or application, and 
who bears the legal product responsibility for the protec-
tion of the user, the staff or for third parties.

Obligations of the operating company

If the crane scales is used for commercial purposes, the 
operating company of the crane scales must comply with 
the legal working safety regulations. Therefore, the 
safety notes in this operating manual, as well as the 
safety, accident prevention and environment protection 
regulations applying for the area of application of the 
crane scales must be met. The following applies in par-ti-
cular:

- The operating company must be informed about 

the applying industrial safety regulations and fur-
ther analyse hazards resulting from the special 
working conditions at the place of use of the crane 
scales. She must implement these in form of oper-
ating manuals for the operation of the crane 
scales.

- During the entire lifetime of the crane scales, the 

operating company must verify whether the oper-
ating manuals prepared by her correspond to the 
current status of the regulations, and must adapt 
these if necessary.

- The operating company must unambiguously reg-

ulate and determine the responsibilities for instal-
lation, operation, troubleshooting, maintenance 
and cleaning.

- The operating company must ensure that all per-

sons who work with the crane scales, have read 
and understood this manual. Furthermore she 
must instruct the staff in regular intervals and in-
form them about the hazards.

- The operator must provide the necessary protec-

tive equipment to the staff and order the use of the 
necessary protective equipment in a binding way.

Furthermore the operating company is responsible to 
keep the crane scales always in a technically flawless 
state. Thus, the following applies:

- The operator must ensure that the maintenance in-

tervals described in this manual are kept.

- The operator must have all safety devices checked 

regularly for their good working order and their in-
tegrity.

WARNING!

This combination of symbol and signal words indi-
cates a potentially dangerous situation which may 
lead to death or severe injury if not prevented. 

CAUTION!

This combination of symbol and signal words indi-
cates a potentially dangerous situation which may 
lead to slight or minor injury if not prevented. 

ATTENTION!

This combination of symbol and signal words indi-
cates a possibly dangerous situation which may lead 
to property and environmental damages if they are 
not avoided.  

NOTE!

This combination of symbol and signal words indi-ca-
tes a potentially dangerous situation which may lead 
to material and environmental damage if not preven-
ted.

Tips and recommendations

This symbol highlights useful tips and recommenda-
tions as well as information for an efficient and trou-
ble-free operation.

Summary of Contents for KW 50

Page 1: ...KW S ERIES KW 50 Operating Instructions Crane scale KW 50 KW 100...

Page 2: ...2 1 Symbol explanation 3 2 2 Obligations of the operating company 4 2 3 Requirements to staff 5 2 4 Personal protective equipement 5 2 5 General safety regulations 6 2 6 Safety information of operatin...

Page 3: ...We are always interested in valuable experience and knowledge gained from using the application which then could be shared and be valuable to develop our products even further 1 3 Limitation of liabil...

Page 4: ...ecessary The operating company must unambiguously reg ulate and determine the responsibilities for instal lation operation troubleshooting maintenance and cleaning The operating company must ensure th...

Page 5: ...ct our cus tomer service for the execution of all arising work 2 4 Personal protective equipment The personal protective equipment serves to protect per sons against impairments of safety and health w...

Page 6: ...ility Insurance Association the Central Agency for Accident Prevention the Test Guidelines and the test regulations according to DIN 685 Part 5 Nov 1981 UVV DGUV Regulation 54 and UVV DGUV Regulation...

Page 7: ...cidents or damage caused by these resi dual risks Risk of crushing of upper and lower limbs while equipment is operating During set up and adjustment works it may be come necessary to remove safety de...

Page 8: ...kaging All used packaging materials and packaging aids are recyclable and should be taken to a materials recycling depot to be disposed of The delivery packaging is made of cardboard so please dispose...

Page 9: ...alling or whose parts are not firmly connected Never use a rusted or damaged Crane scale Never leave a load lifted by the crane scale unatten ded When lifting or lowering a load make sure that the ope...

Page 10: ...lifted with the Crane scale Do not make any sudden changes in the direction of movement Never hang heavy loads for long periods of time to minimize the load on the crane scale and prevent accidents W...

Page 11: ...t is lb kg kg Lights when the unit is kg Report stands for Annotation The weight is above the defi ned range Determination of the weight stabilization phase The weight is below the defi ned range SETU...

Page 12: ...off The Symbol TARE shines a The balance must not be locked otherwise the symbol will be displayed Locking unlockingif you want to lock the scale The symbol Step 1 Press or if you want to lock the sc...

Page 13: ...t 2000 to 3000 divisions Step 3 The default resolution will be restored the next time the balance is turned on or user settings are made If you want to use the changes later then save the new resoluti...

Page 14: ...the safety of the hook is closed NOTE The automatic shutdown can be set to the following values 0 never 5 min 15 min 30 min 60 min ATTENTION The Auto Off feature maximizes battery life It starts the...

Page 15: ...ry should be stored bet ween 20 C 4 F and 50 C 122 F The bat tery should be charged every three months 6 When charging the battery the green charging indica tor light comes on If the lamp is red charg...

Page 16: ...r the load hook After each use Relieve the crane scales immedi ately after each use Oil the load hook and the lifting eye well 40 hours Lubricate all bearings upon need Replacement of lifting eye and...

Page 17: ...d dusty or ag gressive environment high switching frequency high duty cycle the test intervals must be shortened Expert for the inspection of cranes apart from the experts of the T V only the experts...

Page 18: ...ale for repair Display does not show 0 after discharge Tare set Warm up time of the Crane scale too short 1 Set tare 2 Longer warm up time The Button The button re mains pressed after being pressed 1...

Page 19: ...ispatched at the discretion of the supplier Information about the device type item number and year of manufacture can be found on the type plate The type plate is mounted on the device Example The loa...

Page 20: ...ing should help you to identify necessary spare parts in case of service If necessary send a copy of the parts drawing with the marked components to your authorized dealer Fig 8 Spare parts drawing 14...

Page 21: ...Electrical wiring diagram KW Series Version 1 03 21 Circuit diagram Fig 10 Circuit diagram of KW 50 and KW 100...

Page 22: ...cluding any changes in force at the time of declaration Relevant EU directives 2014 35 EU Low Voltage Directive The following harmonized standards were applied DIN EN ISO 12100 2010 Safety of machines...

Page 23: ...n 1 03 23 16 Maintenance plan Maintenance plan KW 40 h 200 h Requirement yearly Lubricate bearings wear measurement Lifting eye hook replacement Lifting eye hook Sicherheitspr fung Crane scale Date Op...