| 20
C64.65201 Issue 3
Jun 2019
Preparing and Mounting the Signal Head
Where the signal is to be installed in a Unipart Dorman ALT the standard CLS LITE
base plate is replaced by a Spigot Bracket which fits into the GRP Post and where all
of the angles are set during manufacture to enable signal alignment from ground
level.
Where the head is to be fitted to the GRP Post and ALT, it will arrive upright on a
pallet secured to a special to type mount. To remove it from the Pallet remove and
retain the grub screws shown in blue above and slide the collar (in green) to the
bottom of the mounting fixture. It is strongly recommended that the signal is
removed from the transport fixture with mechanical lifting equipment using the
lifting eyes provided.