| 5
C64.65201 Issue 3
Jun 2019
Pre Installation Checks
It is assumed that the mounting/foundation for the particular signal has been
installed and has been accepted by the person responsible for structures prior to
commencement of the installation.
The signal should be checked for damage and any remaining transit packing
materials should be removed and correctly disposed of.
The signal modules each weigh 5.5 Kg and can be removed to lighten the signal for
lifting during installation. This is covered in the Module Replacement section of this
document.
BEFORE THE COMMENCEMENT OF ANY ACTIVITY, ARRANGEMENTS
SHALL BE APPLIED TO PROTECT THE WORKING RAILWAY.
CLS LITE Variants
There are two types of CLS LITE head and they are defined by the way they are
mounted. The installation instructions are different and it is important that you
identify which variant you are installing.
CLS LITE was originally designed to be used on ‘conventional’ non-folding structures
such as gantries and standard signal posts and also the Collis Folding Post.
It is supplied with the standard baseplate mandated in NR/SP/SIG10062.