Note that if power remains applied to the panel during breaker installation the alarm 
LED will show red and the alarm relay will be activated until the new cables have been 
connected and the breaker set to the ON position.

13.0  SETUP AND TESTING

13.1

 

It is not necessary to have the distribution panel mounted in a rack for initial testing.  This 
can be done on a bench.  It is also not necessary to have loads connected to the panel for 
this testing.

13.2

  With the input power source off, connect the input wires to the A side of the distribution 

panel.  Connect ground to the chassis ground terminal.  Set all circuit breakers to on.

13.3

 

Turn on the input power source.  The A side LED should be green.  If it is red, one of the 

circuit breaker is tripped.  If the LED is off, there is no input power to the unit.  Check the 

output voltage at each set of output terminals with a digital voltmeter.

13.4

  

With the A side LED green, use an ohmmeter to check the Form C relay contact outputs.  
On J4 measure the resistance between pins 1 and 2.  This should read “open”.  Measure the 
resistance between pins 2 and 3. This should read “short”.

13.5

 

On the A side trip circuit breaker no. 1.  The A side LED should turn red. On J4 measure the 
resistance between pins 1 and 2.  This should read “short”. Measure the resistance between 
pins 2 and 3.  This should read “open”. Reset the circuit breaker.

13.6

 

On the A side check each succeeding breaker by tripping it, and verify that the LED turns 
red.  It is not necessary to recheck the Form C relay contacts.

13.7

 

Repeat the same tests of Sections 13.2 through 13.6 on the B side of the distribution panel, 
use J3 to check the Form-C relay operation.

13.8

 

The distribution panel may now be connected to its intended application.

13.9 

 

If the distribution panel did not operate properly in the above tests, go back and double 
check the connections and the polarity of the input source to make sure it is correct.

 

Please note that there are no user serviceable parts inside either the modules or the shelves 
and that opening either will void the warranty.

StockCheck.com

Downloaded from StockCheck.com

Summary of Contents for DPP1U-A1

Page 1: ...ANELS Document Number DPP1U MAN Rev 6 UNIPOWER LLC 65 Industrial Park Rd Dunlap TN 37327 Phone 1 954 346 2442 Toll Free 1 800 440 3504 Web site www unipowerco com 2019 UNIPOWER LLC All Rights Reserved...

Page 2: ...5 4 0 SAFETY INDUSTRY STANDARDS 5 5 0 WARRANTY summary 6 6 0 DESCRIPTION OF OPERATION 6 7 0 SPECIFICATIONS 7 8 0 FRONT PANEL DESCRIPTION 8 9 0 BACK PANEL DESCRIPTION 8 10 0 UNPACKING AND INSPECTION 1...

Page 3: ...ution Panel 4 Figure 2 Block Diagram 6 Figure 3 Front Panel View 8 Figure 4 Back Panel View 8 Figure 5 Input Bus Bar Detail 8 Figure 6 Output Barrier Strip Detail 9 Figure 7 Alarm Contact Detail 9 Fig...

Page 4: ...and alarm capabilities TheAand B sections of the dual bus panel are fully isolated can be separately configured for 12 or 24 48 volts and are polarity neutral Breaker capacities range from 1 to 30 am...

Page 5: ...020 20 348 1436 0050 BLANK 348 1418 0000 Breakers need to be ordered individually and are shipped with each panel as separate items for field installation 4 0 SAFETY INDUSTRY STANDARDS 4 1 DPP1U Serie...

Page 6: ...zed by the manufacturer or to products which become defective due to acts of God negligence or the failure of customer to fully follow instructions with respect to installation application or maintena...

Page 7: ...Neutral Positive or Negative Ground ALARMS Alarm Indicator Dual Color LED Per Bus LED Status Indication Green Normal Red CB Trip Alarm Off No Power Alarm Relays Form C Contacts for each Bus SAFETY UL...

Page 8: ...iew 9 0 BACK PANEL DESCRIPTION 9 1 Back View Figure 4 shows the back of the DPU1U distribution panel Inputs are at the left and right ends of the back panel Side B outputs are at two rows of barrier t...

Page 9: ...140 1 1 2 LCA1 14 E LCD1 14A E 625 1665 0050 625 1665 0150 9 4 Output Connections Output connections for A and B loads are shown in Figure 4 There are 8 sets of barrier terminal strip connections for...

Page 10: ...the Form C relay contact terminals is the chassis ground terminal This terminal is a no 8 32 stud with a nut NOTE THAT IT IS ESSENTIAL THAT THIS TERMINAL IS CONNECTED TO THE SYSTEM FRAME GROUND TO ENS...

Page 11: ...n ALM B ALM A BAT BAT RTN RTN NO C NC NO C NC BAT RTN BAT RTN 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 ALM B ALM A BAT BAT RTN RTN NO C NC NO C NC BAT RTN BAT RTN 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 ALM B ALM A BA...

Page 12: ...ALM A BAT BAT RTN RTN NO C NC NO C NC BAT RTN 1 2 3 1 2 3 4 5 6 7 8 150A MAX PER BUS A B ALARM 1 1 8 ON I O OFF ON I O OFF ON I O OFF ON I O OFF ON I O OFF ON I O OFF ON I O OFF ON I O OFF ON I O OFF...

Page 13: ...13 4 With the A side LED green use an ohmmeter to check the Form C relay contact outputs On J4 measure the resistance between pins 1 and 2 This should read open Measure the resistance between pins 2 a...

Page 14: ...rk Rd Dunlap TN 37327 United States Manufacturing facility UNIPOWER Slovakia SRO ZLATOVSKA 1279 Business Center 22 91105 Trencin Slovakia Phone 1 954 346 2442 Toll Free 1 800 440 3504 Web site www uni...

Reviews: